FusionModule5000 Smart Modular Data Center
Installation Guide (Single-Row Aisle Containment with
2000 mm High Cabinets, ECC800)
4 Hardware Installation Preparations
Issue 01 (2019-03-05)
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
36
Figure 4-22
Tightening expansion bolts
Step 8
Secure the base to the adjacent bases using two M8 screws and nuts, as shown in
Figure 4-23
Connecting the base to the adjacent bases
Step 9
Follow the preceding steps to install other bases.
----End
4.2 Preparing for Installing Air Conditioners
4.2.1 Material Preparations
Materials are classified to Huawei-provided, self-purchased, and onsite prepared materials,
which are marked as mandatory, optional, and engineering purchasing in this document.
Mandatory: materials that are provided by Huawei and can be obtained from delivered
fittings