FusionModule5000 Smart Modular Data Center
Installation Guide (Single-Row Aisle Containment with
2000 mm High Cabinets, ECC800)
9 Installing Monitoring Devices
Issue 01 (2019-03-05)
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
148
Figure 9-52
Installing a pad
----End
9.8.6.7 Securing the Pad Mounting Kit
Procedure
Step 1
Lay out the cables of monitoring components on the pad mounting kit, as shown by (1) in
Step 2
Clamp the pad mounting kit to the hanging kit, as shown by (2) in
Step 3
Secure the pad mounting kit to the hanging kit using two M5x10 tapping screws, as shown by
(3) in