FusionModule5000 Smart Modular Data Center
Commissioning Guide
6 Commissioning the Management System
Issue 06 (2020-03-20)
Copyright © Huawei Technologies Co., Ltd.
82
To ensure the normal operating of the ECC800, avoid high data traffic, such as the
concurrent display of dynamic monitoring of cameras and VCN500 video playback.
To ensure the normal operating of the ECC800, you can view the videos from a maximum
of two IPC6325-WD-VR cameras concurrently.
LAN Switch Networking Scenario
There are multiple VCNs for multiple smart modules, you are advised to evenly distribute the
cameras to each VCN.
Figure 6-25
VCN connecting to the LAN switch
6.6.5.2 Commissioning a Camera (Smart ETH Gateway Networking
Scenario)
If the camera web version is IPC V200R003C00, refer to this topic to commission the camera.
6.6.5.2.1 Commissioning IPC6325 Cameras
Prerequisites
If multiple cameras are accessed, retain the connection of one camera and disconnect
connections from other cameras. After commissioning the connected camera, commission
other cameras in the same way.
Ensure that the camera has connected to the smart ETH gateway and the smart ETH gateway
communicates properly with the ECC800.
Context
The existing network is equipped with the ECC800 that supports the Dynamic Host
Configuration Protocol (DHCP). After the ECC800 and IPC6325 camera are powered on,