FusionModule5000 Smart Modular Data Center
Commissioning Guide
5 Commissioning the Cooling System
Issue 06 (2020-03-20)
Copyright © Huawei Technologies Co., Ltd.
49
Figure 5-18
Commissioning successfully
is displayed if component commissioning fails, which ends startup wizard
commissioning.
Figure 5-19
Commissioning unsuccessfully
If commissioning fails, tap
Commissioning failed.
----End
5.9 (Optional) Power-off
Context
In shutdown mode, the
Shutdown
button is green (unavailable) and the
Start
button is gray
(available).
Procedure
Step 1
Tap
Shutdown
on the home screen. A warning is displayed, indicating whether to shut down
the smart cooling product, as shown in