FusionModule2000 Smart Modular Data Center
Installation Guide
5 Installing the PDC
Issue 02 (2018-03-31)
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
55
1.
Check the exterior of the PDC and check whether the PDC is damaged during
transportation. If any damage is found, notify the carrier immediately.
2.
Check that the fittings comply with the packing list. If some fittings are missing or do
not comply with the packing list, record the information and contact your local Huawei
office immediately.
Step 5
After verifying that the PDC is intact, remove the L-shaped brackets securing the cabinet and
pallet, and insert the two sliding plates under the pallet.
Ensure that the sliding plates are properly installed in step (2) in
; otherwise, the sliding plates
may shift when the PDC is unloaded.
Figure 5-1
Removing an L-shaped bracket
Step 6
Raise the four leveling feet to the highest position using an adjustable wrench.