6.1 Replacing Power Supply and Distribution System
Components
6.1.1 Replacing a PD510
Prerequisites
A PD510 electricity meter needs to be replaced.
A spare PD510 electricity meter of the same model is available and functional.
Impact on the System
Certain services in the FusionModule1000 are interrupted.
Preparations
Tools: Phillips screwdriver, protective gloves
Materials: spare PD510 electricity meter
Documents: documents delivered with the PD510 electricity meter, management system
initial configuration table
Skill requirement: power distribution system engineer
For the table, see the initial configuration parameter manual for the solution in use.
Procedure
Step 1
Disconnect the upstream fuse of the PD510 electricity meter.