Figure 7-21
Site Opstart dialog box
Step 9
Choose
Cell0
>
Cell Opstart
>
OK
. The
Cell Opstart
dialog box is displayed, as shown in
.
If...
Then...
Cell Opstart successfully is displayed
Click
Close
and proceed with the next step.
Cell operation start fails
See
.
Figure 7-22
Cell Opstart dialog box
Step 10
The site configuration takes effect.
Step 11
Make the attributes of other TRXs take effect: Choose
BT0
>
BT Opstart
>