Periodic maintenance 62
Periodic maintenance
Periodic maintenance overview
Perform periodic inspections on the components in this section to ensure that the HP POD 40c NA continues
to perform within the designed parameters.
Qualified personnel
Qualified personnel are identified as personnel who are:
•
Properly trained in the operation and maintenance of the HP POD 40c NA
•
Customer-authorized to conduct maintenance activities
Qualified personnel can be:
•
HP personnel
•
Agents for HP
•
Site maintenance personnel
Cooling system maintenance schedule
Component to be inspected
Task
Frequency
Capable Party
Air filters
Inspect and replace as necessary Quarterly, or as
needed
Qualified personnel
Air filter differential pressure
sensor
Inspect and test, replace as
necessary
Annually
Qualified personnel
Cooling system leak check
Verify there is no visible chilled
water leak from:
•
Heat exchanger
•
Cold water supply piping
•
Cold water return piping
If a leak is detected, see "Leak
detection maintenance (on page
Quarterly
Qualified personnel
Condensate drain pans
Inspect pans:
•
Free of debris
•
No leaks
•
Leakage detectors are in
proper position
Clean pans as necessary
Quarterly
Qualified personnel
Condensate drain pan sensors
Inspect and test, replace as
necessary
If a leak is detected, see "Leak
detection maintenance (on page
Quarterly
Qualified personnel