6
2.
Assembly
2.1
Installation, levelling
A special foundation plate for the boiler is not an essen
-
tial, but it is recommended.
Space required
the flange of the boiler must be able to be swung out fully,
with burner installed (see chapter 3.3).
CAUTION
Electric wires must not be permitted
to touch any hot parts!
Fig. 01
Installing the boiler
Fig. 1
Remove the two upper bolts (1) at the foot (1a) of
the boiler.
Fig. 2
Take off the transverse timber beam at the front.
Fig. 3
Use a winch (2) to lift the front of the boiler.
Fig. 4
Take away the side beams (3) at the front sideways
(see Fig. 01). Fit the forward feet and bolt them into
place.
Fig. 5
Use the winch (2) to lift the rear of the boiler.
Fig. 6
Take away the side beams (3) at the rear sideways
(see Fig. 01). Fit the rear feet and bolt them into place.
Only to be observed if neutralisation is required:
Setting the height of the feet is carried out af
-
ter installation of the neutralisation fitting
3
1a
1
2
Lifting eyes for crane hooks
a
4 213 787 / 01
ASSEMBLy