INSTALLATION

When Installing this product…

1. Read these instructions carefully. Be sure to follow

Warning information carefully.

2. Check the ratings given in the instructions and on the

product to make sure the product is suitable for your
application.

3. Installer must be a trained, experienced flame

safeguard control technician.

4. After installation is complete, check out product

operation as provided in these instructions.

WARNING

Explosion Hazard And Electrical Shock Hazard.
Can cause explosion, serious injury or death.
Turn off gas supply before starting installation.
Disconnect power supply before beginning installation.
More than one disconnection can be involved.

Mounting

Refer to the Integrated Valve Train Installation Instructions,
form 66-1099, for instructions on mounting a V4297S
between two Safety Shutoff valves.

WIRING

1. Make sure that all wiring agrees with all applicable local

codes, ordinances and regulations. An opening is
provided to accommodate rigid conduit or armored
cable for line voltage operation (see Fig. 4).

G

L2

4

9

RM7800
(TYPICAL)

120 Vac

N

L

V4297S

M16463

GROUND

NEUTRAL

MAIN VALVE

LINE
VOLTAGE

2. Check the power supply circuit to verify the voltage and

frequency are the same as for the valve.

3. See Fig. 5 for typical V4297S field wiring with the

RM7800 Relay Module. Follow the burner manufacturer
wiring diagram, when provided. Refer to the relay
module wiring diagram for specific wiring terminal
designations.

4. Make wiring connections at the electrical terminations

provided in the valve wiring compartment.

Fig. 4. Wiring compartment of V4297 NOVV.

Fig. 5. Typical wiring diagram for V4297 NOVV.

OPERATION AND CHECKOUT

Operation

The V4297S is a normally open valve. The valve closes when
it is energized, and opens when the power is removed. It
provides the vent function in a double block and bleed
application. The V4297S is open when the two Safety Shutoff
Valves (SSOV) are closed, and is closed when the two SSOV
are open.

Checkout

WARNING

Explosion Hazard And Electrical Shock Hazard.
Can cause explosion, serious injury or death.
1.
 Do not put the system into service until you have

satisfactorily completed the following Valve Leak
Test, all applicable tests described in the Checkout
section of the instructions for the flame safeguard
control, and any other tests required by the burner
manufacturer.

2. All tests must be performed by a trained,

experienced, flame safeguard control technician.

3. Close all manual fuel shutoff valves as soon as

trouble occurs.

After the installation is completed, cycle the valve several
times with the manual fuel shutoff cock closed. Make sure the
valve functions properly. Also perform the Valve Leak Test
before putting the valve into service.

Содержание V4297S

Страница 1: ... The gas flows through the vent connection when the valve is not energized V4297S are used with 110 120Vac 50 60Hz controllers Two valve body types small and large applicable to seven pipe sizes Small body type for 3 4 in 19 mm 1 in 25 mm 1 1 4 in 32 mm 1 1 2 in 38 mm and 2 in 51 mm pipes Large body type for 2 in 51 mm 2 1 2 in 64 mm and 3 in 76 mm pipes Small body has a 1 in NPT threaded vent con...

Страница 2: ...his product is tested and calibrated under closely controlled conditions and some minor differences in performance can be expected if those conditions are changed Models V4297S Normally Open Vent Valve Type of Gas Natural manufactured mixed or liquefied petroleum LP only Gas Train Pipe Size 3 4 in 19 mm 1 in 25 mm 1 1 4 in 32 mm 1 1 2 in 38 mm 2 in 51 mm 2 1 2 in 64 mm 3 in 76 mm Pipe Threads Smal...

Страница 3: ... 2 Approximate dimensions of smaller V4297 NOVV in in mm 3 8 10 3 HOLES 2 5 8 69 9 1 2 241 3 1 8 79 3 8 10 1 2 13 1 2 13 7 8 22 4 1 8 105 3 1 8 79 5 127 3 8 10 1 2 13 1 1 4 32 2 51 1 1 2 32 3 16 5 1 1 4 32 1 15 16 49 2 3 8 60 M16464 2 51 1 IN NPT ...

Страница 4: ...ll V4297S complete with wiring box BBA51317 Coil for large V4297S complete with wiring box Approvals Underwriters Laboratories Inc Listed Industrial Risk Insurers formerly FIA Acceptable International Approval Services IAS Design Certified 2 5 8 69 3 76 1 1 2 38 5 16 8 1 2 13 3 4 18 3 4 18 2 51 5 127 8 203 1 1 2 32 3 16 5 M16465 2 51 12 3 8 314 3 1 8 79 1 2 13 4 1 2 114 5 8 16 1 25 1 1 4 IN NPT 1 ...

Страница 5: ...e Fig 5 for typical V4297S field wiring with the RM7800 Relay Module Follow the burner manufacturer wiring diagram when provided Refer to the relay module wiring diagram for specific wiring terminal designations 4 Make wiring connections at the electrical terminations provided in the valve wiring compartment Fig 4 Wiring compartment of V4297 NOVV Fig 5 Typical wiring diagram for V4297 NOVV OPERATI...

Страница 6: ...erminal block make sure all appropriate contacts in the thermostat or controller limits and flame safeguard controls are closed If one or more are open determine the cause s correct the trouble and proceed 4 If there is proper voltage at the valve but the valve still does not close check for normal gas pressure 5 If the valve still does not close replace the valve If the valve does not open when o...

Страница 7: ...V4297S NORMALLY OPEN VENT VALVE 65 0244 7 ...

Страница 8: ... and Building Control Honeywell Limited Honeywell Limitée 155 Gordon Baker Road North York Ontario M2H 3N7 Honeywell Latin American Region 480 Sawgrass Corporate Parkway Suite 200 Sunrise FL 33325 65 0244 G R 6 99 Home and Building Control Honeywell Inc Honeywell Plaza P O Box 524 Minneapolis MN 55408 0524 www honeywell com Printed in U S A on recycled paper containing at least 10 post consumer pa...