background image

Document 800-06748 – Rev A – 01/11

10X True Day/Night PTZ Dome Quick Installation Guide

Document 800-06748 - Rev A - 01/11 

Overview

Set the Protocol, Terminal Resistor, and Address

1.

Set the communication protocol of the dome by selecting one 
of the following combinations on the 4-pin DIP switch:

Note

Only Pelco-D protocol is supported in this firmware version.

2.

Set the terminal resistor of the dome to ON or OFF using pin 4 on 

the 4-pin DIP switch. Set the terminal resistor to ON if:

You are connecting a single dome to the controller.

The dome is last on a communication line with multiple 
domes installed. The dome farthest away from the controller 
must have the terminal resistor set to ON. All other domes 
connected to the same cable must be set to OFF (see below).

Note

RS-485 cabling should always be terminated at each end of the chain,
even on short runs.

3.

Set the address of the dome on the 8-pin DIP switch, 
using the tables below as a reference. The address 
must be within the range allowed by the protocol you 
are using. The factory default is 1. 

Install the Dome

Using Surface Mount Bracket

1.

If necessary, cut a small hole in the ceiling 1 1/4 –1 1/2 inches (30–40 mm) in 
diameter for wiring and cabling to pass through.

2.

Connect the power, video, and data wiring to the main 
cable, and then route the main cable through one of the 
access holes in the surface mount bracket.

3.

Attach the surface mount bracket to the ceiling using the 
four supplied M4×25 screws (Fig. 1).

4.

Connect the main cable to the main body.

5.

Attach the main body to the surface mount bracket using 
the three supplied M3×8 screws (Fig. 2).

6.

Align the guide on the dome cover with the left guide on 
the main body flange, and then twist the dome cover 
clockwise until it locks into place (Fig. 3, Fig. 3A).

7.

Secure the dome cover to the main body using the supplied M3×6 lock-up screw 
(Fig. 3).

8.

Remove the protective vinyl from the dome cover.

Note

If the wiring access hole on the side of the surface mount bracket is not used, plug 
the hole with the supplied rubber gasket.

All types of installations must be performed by qualified technical personnel and must be in accordance with all national and local mechanical and electrical codes.

Ensure that the mounting surface can support the combined weight of the main body, dome cover, housing, and mount. Use the best installation practices for the structure and material to 
which the mount is being attached.

Cable preparation should be completed prior to the installation. Each dome requires 9.6 W minimum, 12 V DC or 24 V AC (measured at the dome). The power supply should be located as 
close to the dome as possible for service and electrical isolation purposes. To prevent damage to the electronic components of the dome, follow standard industry precautions for 
electrostatic discharge (ESD) sensitive devices.

These instructions are only a basic guide. Refer to the 

10X True Day/Night PTZ Dome User Guide

 for detailed safety and installation information not included here.

Protocol

DIP Switch

Pin  1

Pin  2

Pin  3

Pelco-D, 2400 bps

OFF

OFF

OFF

Pelco-D, 9600 bps

ON

OFF

OFF

Surface Mount Bracket

Main Body

Dome Cover

Main Cable

Hardware Kit

Main  Cable

4 - M4×25  screws

3 - M4×50  screws

3 - M4 nuts

3  -  M3×6  screws

3  -  M3×8  screws

1 - Rubber gasket

Lock-up 
Screw

Main Connector

Location of 
DIP switches

In-Ceiling Ring

1

2

3

4

ON

ON

Protocol Setting

1

2

3

4

ON

ON

Terminal Resistor ON

Controller / DVR

Terminal Resistor ON

#1

#2

#n

RS-485

Terminal Resistor

OFF

Terminal Resistor

OFF

Terminal Resistor

ON

1

2

3

4

5

6

ON

ON

7

8

DIP Pin Number

Binary Value

Bit Number

1

1

0

2

2

1

3

4

2

4

8

3

5

16

4

6

32

5

7

64

6

8

128

7

Protocol

Dome Address

Range

Pelco-D

Binary Value

1 – 255

Default Address Setting

Fig. 1

Fig. 2

Fig. 3

Fig. 3A