COMMISSIONING AND DECOMMISSIONING
Information for general use
Rev. M / 73023639
79
GasLab Q2
6.
Commissioning and decommissioning
Do not carry out any of the work described in this chapter if you do not have
permission and have not received the required training from the manufacturer or its
agents.
N’effectuez pas les travaux décrits dans ce chapitre, si vous ne disposez pas
de l’autorisation ni des instructions du fabricant ou de ses agents!
The commissioning procedure may only be carried out by qualified technician or field service
personnel. Honeywell can provide training and commissioning services.
Before commissioning, make sure that Chapter
2 Safety and warning information
observed and followed and that the GasLab Q2 has been installed and connected in accordance
with this document.
All new devices are supplied with default parameter set also called parameterization, which enables
them to perform the measuring task. If you are not familiar with the operation and software of the
instrument, please read first the chapters
7 GasLab Q2 Displays (Operate the Device)
8 Configuration and analysis software enSuite
of this document before you continue.
Refer to the regulations for explosion protection and the safety information, particularly
for starting up the device in a potentially explosive atmosphere.
Les exigences relatives à la protection contre les explosions et à la sécurité doivent être
respectées, en particulier lors de la mise en service dans une atmosphère explosible.
6.1.
Commissioning preparations and requirements
The following points must applie:
•
The upstream sample handling and conditioning system must be operating
properly, providing the correct pressure to the device, and at its operating
temperature.
•
An operational calibration gas cylinder is correctly connected.
•
Delivery is less than 1 year ago, (battery charge above 20%). If you are unsure
check according to hints in section
the battery replaced as a precaution.
•
The device is installed and fully closed.
•
There is no moisture condensation inside the device. If in doubt, remove the
covers (see next section) and allow the appliance to dry for at least 12 hours;
or contact Honeywell.
•
Power supply and communications are carried out properly and is
available
.