WA1
WA2
WA1_QA1
(SESRSYN 1)
WA2_QA1
(SESRSYN 3)
TIE_QA1
(SESRSYN 2)
LINE1
LINE2
LINE1_QB9
LINE2_QB9
IEC11000274-3-en.vsd
IEC11000274 V3 EN-US
Figure 33:
Objects used in the voltage selection logic
11.10.1.5
Completing the test
M2377-1042 v5
Continue to test another function or end the test by changing the
TESTMODE
setting to
Off
. Restore
connections and settings to the original values, if changed for testing purposes.
11.10.2
Autorecloser for 1/2/3-phase operation SMBRREC
M12400-2 v12
Verification of the auto recloser for single-phase, two-phase or three-phase auto reclosing attempts
can be considered to consist of two parts.
•
One part to verify the internal logic and timing of the auto recloser
•
One part to verify its interaction with the protection system
This section deals with verification of the auto recloser itself. However, it is practical to start the auto
recloser by activating a protection function, for example, by secondary injection tests.
Prepare the IED for verification of settings outlined in Section
"Preparing the IED to verify settings"
The purpose of verification before commissioning is to check that entered selections, setting and
configuration render the intended result. The auto recloser is flexible with many options and facilities.
At commissioning only the selections and settings intended for use are verified. If one chooses to
reduce some time settings in order to speed up verification, be careful to set the auto recloser at
intended operational values at the end of the verification procedure. One such parameter is the
tReclaim
time that must be timed out before a new test sequence can be performed.
The verification test is performed together with protection and trip functions.
illustrates a suggested testing arrangement, where the circuit-breaker (CB) is simulated by
an external bi-stable relay (BR), for example a relay type RXMVB2 or RXMD or Breaker Simulator of
Hitachi Power grids. The following manual switches are used:
Section 11
1MRK 511 403-UEN Rev. L
Testing functionality by secondary injection
164
Bay control REC670
Commissioning manual
© 2017 - 2022 Hitachi Energy. All rights reserved
Содержание REC670
Страница 1: ...Relion 670 SERIES Bay control REC670 Version 2 2 IEC Commissioning manual ...
Страница 2: ......
Страница 28: ...22 ...
Страница 54: ...48 ...
Страница 60: ...54 ...
Страница 66: ...60 ...
Страница 90: ...84 ...
Страница 212: ...206 ...
Страница 218: ...212 ...
Страница 232: ...226 ...
Страница 240: ...234 ...
Страница 241: ...235 ...