steel cables assemble
Two-post Clear floor Lift
Two-post Base plate Lift
1. ADJUST SYNCHRONIZING CABLES
Carriages must be on first set of locks. Use vise grips to hold the cable fitting, meanwhile, use a
wrench to tighten the cable nut. Make sure the two cables have the same tension so the carriages
lift at the same time.
If the carriages do not synchronize when lifting, please read below
a. Press UP button to lift the carriages up to the position where the first safety lock of one carriage
is higher than the safety lock on the column. Lower the lift until the lower of the two carriages makes
contact with the safety lock on the column.
b. Loosen the safety lock cable. Release the safety lock on the side where the carriage is in the
higher position. The other side of the safety lock should be engaged at this time. Then lower the lift
and the side with the carriage in the lower position will remain locked in the same place and the
other side (higher side) is unlocked. Continue to lower down the lift until the higher carriage is at the
same level as the lower carriage.
c. Loosen the jam nut on the higher carriage synchronizing cable and tighten the tension nut until
the synchronizing cable has the same tension as the other synchronizing cable. Tighten the jam nut
and safety cable
Содержание YL-240
Страница 13: ...oil tubes Two post Clear floor Lift Two post Base plate Lift ...
Страница 14: ...Concrete strength ...
Страница 18: ......
Страница 21: ...4 Oil leakage outside 5 The sound is uncommon ...