Heatrae Sadia Multipoint 30H Скачать руководство пользователя страница 13

13

9.2  Standard inspection & maintenance 

operations

To descale:

 

`

Switch off and disconnect the electrical supply. 

Turn off the water supply to the product.

 

`

Open a hot tap to relieve any system pressure. 

Disconnect the plumbing connections to the 

product and remove from the wall bracket (note 

full weights of product). Empty the product by 

opening the drain valve in the inlet pipework.

 

`

Remove the terminal cover by using a large flat 

bladed screwdriver to depress the 4 snap lugs 

located in the top 4 rectangular depressions.

 

`

Disconnect the electrical terminations to the 

thermostat. Disconnect earth links to the 

earthing stud.

 

`

Remove the element plate assembly by 

unscrewing the five securing screws, a tapped 

jacking point is provided. Remove any loose 

scale from the container. Carefully clean off any 

scale from the element and thermostat pocket. 

DO NOT clean scale from interior container 

walls.

 

`

Re-assemble the element plate assembly fitting 

a new sealing gasket. Rewire the product with 

reference  to  the  Wiring  Diagrams.  Refit  the 

insulating pad to ensure the correct operation of 

the thermostat.

 

`

Re-commission the product following the 

Installation and Commissioning instructions.

 

`

The Temperature/Pressure Relief Valve and, 

if  fitted,  the  Pressure  (expansion)  Relief  Valve 

should be regularly checked. This is to remove 

lime scale deposits and to verify that it is not 

blocked. To check the valves:

•  Manually operate the valves by either twisting 

the cap or lifting the lever. Ensure water 

flows freely from the valve(s) and through the 

discharge pipes. Ensure the valve(s) reseat 

correctly when released.

 

`

The Expansion Vessel, should have a precharge 

pressure of 0.35 MPa (3.5 bar). This can reduce 

over time and eventually require re-charging. To 

do this:

•  Turn off water supply to the product; open a 

hot tap to relieve system pressure.

•  Remove dust cap from top of Expansion 

Vessel

•  Check pre-charge pressure using a tyre 

pressure gauge. If the pressure is lower than 

0.35 Mpa (3.5 bar) it should be recharged 

using a tyre pump (Schraeder Valve type). 

DO NOT OVER CHARGE.

•  Re-check pressure and when correct replace 

dust cap.

•  Turn on mains water supply and close hot 

tap.

9.  Maintenance

9.1 General

Maintenance requirements

Unvented hot water systems have a continuing 

maintenance requirement in order to ensure safe 

working and optimum performance. It is essential that 

the relief valve is periodically inspected and manually 

opened to ensure no blockage has occurred in the 

valves or discharge pipework. Maintenance of this 

appliance should only be carried out by a suitably 

qualified person. Failure to do so could invalidate the 

warranty

WARNING

Disconnect from all electrical supplies 

before beginning any work on the product. 

Water contained within the product may 

be very hot!

Maintenance should be carried out by a 

competent person and any replacement 

parts should be authorised Heatrae Sadia 

spare parts.

It is recommended that maintenance is 

carried out annually and should include 

the checks detailed in the sections below.

Little maintenance is required, however in 

hard water areas the product will require 

periodic  descaling  to  ensure  efficient 

operation. 

Содержание Multipoint 30H

Страница 1: ...Multipoint Horizontal 30 and 50 litre Fitting Instructions...

Страница 2: ...ise warranty details to customers Contents 1 Introduction 3 1 1 General 3 1 2 Symbols used 3 1 3 Abbreviations 3 1 4 Liabilities 3 2 Safety 4 2 1 General safety warnings 4 2 2 Recommendations 4 2 3 Sp...

Страница 3: ...in product quality All the specifications stated in this document are therefore subject to change without notice Our liability as the manufacturer may not be invoked in the following cases Failure to...

Страница 4: ...pass the thermal cut out in any circumstance 2 Safety 2 1 General safety warnings DANGER This product is unvented and as such becomes pressurised when in operation The combination of pressurisation an...

Страница 5: ...posed of at end of life See Section 3 to 11 Electrical rating 3kW 240V 2 75kW 230V Capacities 30 or 50 litres Weight full 30 litre 42 5kg 50 litre 69 3kg Rated pressure 0 6MPa 6 bar Minimum recommende...

Страница 6: ...per inner vessel which ensures an excellent standard of corrosion resistance The outer casing is a combination of resilient thermoplastic moldings and painted steel The product is supplied complete wi...

Страница 7: ...iling and national regulations as listed below Building Regulations The Building Standards Scotland The Building Regulations Northern Ireland I E E Electrical Regs UK Water Regulations 5 2 Installatio...

Страница 8: ...f valve 3 52 Where a manifold is used it should be sized to accept and discharge the total discharge from the discharge pipes connected to it 3 53 Where valves other than the temperature and pressure...

Страница 9: ...ithstanding high temperature discharges of water and 3m from any plastic guttering system that would collect such discharges Tundish 3 54 The tundish should be vertical located in the same space as th...

Страница 10: ...esistance of 4 No 28mm elbows at 1 0m each 4 0m Therefore the maximum permitted length equates to 14m As the actual length is 7m a 28mm D2 copper pipe will be satisfactory Safety device e g temperatur...

Страница 11: ...he electrical supply The indicator light will illuminate during heating When the set temperature is reached the indicator light will go out The set temperature can be adjusted by rotating the knob loc...

Страница 12: ...his pipe must be left open to atmosphere 8 Operation 8 1 General WARNING Do not block or restrict the discharge from any safety valve fitted Do not tamper with any safety valve fitted If water dischar...

Страница 13: ...ure water flows freely from the valve s and through the discharge pipes Ensure the valve s reseat correctly when released The Expansion Vessel should have a precharge pressure of 0 35 MPa 3 5 bar This...

Страница 14: ...relief valve intermittently A Expansion in mains not possible A Fit pack U2 see important installation points B Mains pressure exceeds 0 41 MPa 4 1 bar B Fit packs U1 and U2 C Pack U1 fitted without p...

Страница 15: ...duct can therefore be disposed of through commercial non WEEE waste facilities Heatrae Sadia does not accept any liability under the WEEE directive This product is manufactured from many recyclable ma...

Страница 16: ...hin 60 days of installation the user completes and returns the certificate supplied along with proof of purchase to register the product The product is not covered against damage by frost and the imme...

Страница 17: ...17...

Страница 18: ...18...

Страница 19: ...19...

Страница 20: ...m our website To support our corporate responsibility and sustainability charters and reduce our printed material we encourage you to download product brochures from our website In designing these fil...

Отзывы: