PRE INSTALLATION INSPECTION AND CHECKS

 

3.1 

Each heater and thermostat is manufactured to the highest standard with great care and 
quality materials.  All the goods are thoroughly inspected and tested before leaving the 
manufacturing plant.  They must be handled with care during storage and installation.  Before 
the installation starts it is advised that the heater is checked to ensure the insulation 

resistance reading is above 2MΩ per element at 500 volts dc.

 

3.1.1 

Should the heater fail this test, isolate the power and control circuits (if installed), and follow 
the steps below: 

 

Fill the terminal box with silica gel bags, and replace the terminal box lid. 

 

Leave for 24hrs to draw any moisture out of the heater elements. 

 

If you have a heated blanket, place this over the heater elements to help with the 
drying.  Heater blankets are available to purchase from   

www.exheat-

industrial.com/contact/enquiry

 

 

If the insulation resistance has not been raised to a sufficient level after 24hrs, repeat 
the process above with replacement gel bags. 

 

Should the above not raise the insulation resistance to the required level please 
contact the technical help on our website.  

www.exheat-

industrial.com/contact/support

 

3.2

 

Insulation Resistance (Megger)

 

3.2.1 

The ‘Megger’ should be applied between the phases and earth.  A reading of greater than 

2MΩ at 500 volts dc should be recorded.  Should the whole heater be below this value 

each 

element would need to be checked to ascertain which one was low in resistance. 

3.2.2 

Use the continuity (Ohms) setting on the elements and check the resistance of each element 
matches or is approximately equal to the results as per the electrical test certificate that would 
have been sent with the heater. 

 

4.0 

INSTALLATION

 

4.1 

Carefully remove the packaging from each item and check for damage. Immediately report 
any damage to Exheat Industrial Ltd. 

4.2 

The heater should be securely fixed in position using the pre-drilled fixing holes, and all 
terminal connections checked for tightness before energising. 

4.3 

The appliance must be securely fitted to a wall or floor using only the brackets provided. 

4.3 

The orientation of the heaters must be strictly adhered to with the feet facing down at all 
times. 

4.4 

The installer or end user shall ensure that the unit has free and unrestricted air flow to allow 
natural convection to occur at all times.  

DO NOT COVER

  the  heater  and do not allow 

anything to rest on or against it. This could lead to dangerous overheating and will invalidate 
the hazardous area certification. 

4.5 

At no time is the ambient temperature to be allowed to rise above +40°C (FAW & FAW-C T3 
& T4 variants) Or +60°C (T2 variants).  This can be achieved by the use of Exheat Industrial 
Ltd integral (if option available) or separate flameproof air sensing  thermostats (HFT & AFT 
type). 

4.6 

The STW range may be regulated by an integral or separate industrial air sensing thermostat 
(SAT type) 

 

 

 

Содержание AFT Series

Страница 1: ...RUCTIONS FAW FAW C FAW C T TYPE AIR WARMERS FCR FCR A TYPE CONVECTORS STW STW T SAFE AREA AIR WARMERS HFT AFT SAT TYPE AIR THERMOSTATS Please read these instructions thoroughly before installation and...

Страница 2: ...NECTION 4 6 0 EARTH CONNECTION 4 7 0 OPERATION 5 8 0 MAINTENANCE 5 9 0 MARKING 6 10 0 CERTIFICATION 6 APPENDIX A WIRING DIAGRAMS 7 APPENDIX B HEATER GENERAL ARRANGEMENT DRAWINGS 18 To maintain the equ...

Страница 3: ...se in potentially explosive atmospheres 1 12 All electrical testing must be carried out in a non hazardous area 1 13 Precautions must be taken to prevent damage to machined surfaces and threads of fla...

Страница 4: ...ld be recorded Should the whole heater be below this value each element would need to be checked to ascertain which one was low in resistance 3 2 2 Use the continuity Ohms setting on the elements and...

Страница 5: ...ably certified cable glands and IP washers not supplied and be fitted by a qualified person Any unused entries should remain plugged with the factory fitted certified Ex d plugs if installed or with s...

Страница 6: ...1 All prevailing site safety regulations shall be adhered to at all times 8 2 Equipment shall be checked regularly for any dust accumulation which must be removed from all surfaces 8 3 Before and whil...

Страница 7: ...nths carry out 6 monthly maintenance before energizing 9 0 MARKINGS 9 1 FAW FAW C FCR Range II 2 G Ex e IlC T4 to T2 Gb 9 2 FAW C T and FCR A with Integral Thermostat II 2 G Ex d e IlC T4 to T2 Gb 9 3...

Страница 8: ...7 APPENDIX A WIRING DIAGRAMS...

Страница 9: ...8...

Страница 10: ...9...

Страница 11: ...10...

Страница 12: ...11...

Страница 13: ...12...

Страница 14: ...13...

Страница 15: ...14...

Страница 16: ...15...

Страница 17: ...16...

Страница 18: ...17...

Страница 19: ...18 APPENDIX B HEATER GENERAL ARRANGEMENT DRAWINGS...

Страница 20: ...19...

Страница 21: ...20...

Страница 22: ...21...

Страница 23: ...22...

Страница 24: ...23...

Страница 25: ...24...

Страница 26: ...Thetford IP25 6NG Tel 44 0 1953 886210 Fax 44 0 1953 883853 For sales and new product information see our website www exheat industrial com Author P Bumstead Issue Date April 2019 Issue K_English A4 p...

Отзывы: