HB-TP180/200
Checking Facility for Temperature Control Units
Testing
34
O8354-EN 2018-11
7.2.3 Testing
Fig. 10: Start quality test
Proceed as follows to start the test sequence automatically:
1.
Open the shut-off valve (move the lever upward).
2.
Open the
Service \ TP test
menu page.
3.
Set the
Quality Test
parameter to „ON“.
The quality test starts automatically.
Follow the instructions on the screen.
The current testing step, according to the process diagram
(
page 32), wird im Symbolfeld angezeigt.
NOTICE!
At the end of the test, you can save a CSV file to a
USB data carrier. A test protocol can be generated
by using the VIP diagramming software. You can
download the software on
4.
Carry out safety test (
page 42).