Preparation for Installation
Installation must be carried out by authorized personnel. Follow the steps below:
1. Position the machine on a flat surface and allow at least 50cm clearance on both sides as well as
the back side, this is essential for the hot air ventilation and also to allow enough room for
maintenance personnel to carry out necessary service and maintenance.
2. Adjust the foot stand so that the machine is level and stable.
3. Loosen all packing cable ties and materials in order to free up all machine movements.
4. Connect the power plug to a suitable outlet with at least 10A capacity. Make sure grounded and
reliable.
5. Locate the air hose supplied with the machine. Connect one end to the inlet of the compressed air
water filter at the back side of the machine; connect the other end to a compressed air supply such
as air compressor or central air supply. Make sure the compressed air supply has at least 0.4Mpa (4
bar) of pressure.