TROUBLE SHOOTING

Insufficient Bubbler Flow:

 

Check that the shut-off valve is wide open.  Verify minimum 20 PSI supply pressure. Clean inlet strainer screen located in

the valve body.  Clean rubber orifice in flow control located below frost line in bushing between barb fitting and valve.

No Flow:

 

 Check for leaks in the air tubing going from the push button to the valve.  Make sure the air tubing compression nut is hand tight.  Disconnect air

tube from push button.  Place finger over air outlet. Push button to test diaphragm.  Tighten diaphragm cap screws.  Replace diaphragm if necessary.

Continued Insufficient or Varied Height of Bubbler Flow:

•

 Replace flow control.

•

 Check for kinks in the tubing.

•

 Remove the PVC cap from the PVC column. Remove the valve assembly from the PVC column by carefully pulling up on the connecting tubing. Pressure

test the valve assembly for leaks. Check stream height from the bubbler. Stream height is factory set at 35 PSI. If supply pressure varies greatly from this,

adjust the screw on the regulator (Item 18, Page 5, Stream Height Adjustment Detail). Clockwise adjustment will raise stream and counter-clockwise adjustment

will lower stream. For best adjustment stream height should be approx. 1-1/2" (38mm) above the bubbler guard. Replace the valve into the PVC column. Make

sure the supply hose coils into the bottom of the PVC column without any kinks and double check that the valve is positioned fully at the bottom of the PVC

column. Cap the PVC column.

Continuous Bubbler Flow:

 

Insure that push button is not obstructed and springs back to normal position. Remove four screws which secure plastic

diaphragm block to valve body.  Pull plastic and rubber diaphragm assembly out of valve body.  Locate tiny hole in rubber diaphragm just under lip of plastic

part.  Clean debris from this hole.  Inspect valve seat for grooves.  If valve seat was OK and diaphragm hole was free from debris, inspect rubber button

located at center of floating steel disc in valve diaphragm block assembly.  If button is worn, turn disc over or replace it.  If diaphragm and seats are in good

condition, stretch spring slightly.  Spring is located behind floating stainless steel plate.  Insure that air bleed port on valve plastic block assembly is not

plugged.

INSTALLATION INSTRUCTIONS FOR INSTALLING 97243C

SINGLE VALVE CONTROL ASSY.

1. Prepare trench for water supply and waste drain lines (if required by local codes).  The hole should be deep enough to accommodate the PVC column and 5

cubic feet of porous fill (large broken rock).  Additional porous fill may be required due to local ground conditions. (See Site Preparation Detail below).

2. Lay drain lines and water supply lines. Provide service shut off valve for maintenance. Flush the water supply line before attaching to the shut off valve.

3. Set PVC column in excavating pit.  Connect the water supply line to the inlet on the PVC column.  Remove valve assembly from the PVC column by

carefully pulling up on the connecting tubing.  Pressure test the valve assembly for leaks.  Check operation of the water valve by blowing on the small

clear diameter tubing. A steady stream of water should flow from the braided tubing.  After releasing air pressure from the small clear tubing the water

stream should stop.

4. Replace the water valve into the PVC column.  Make sure the supply hose coils into the bottom of the PVC column without any kinks. Cap the PVC

column, protect the ends of the connecting tubes and backfill the trench.  Keep the PVC column vertical at all times.

5. Form the concrete mounting pad and locate the fountain anchor bolts in the proper position.  (Refer to Rough-in for correct location of anchor bolts.)  Pour

concrete and finish.  Be sure to keep concrete away from the top of the PVC column to allow removal of PVC cap to allow for future service.  Let concrete

set 24 hours minimum before mounting fountain.

6. Double check that the water valve is positioned fully at the bottom of the PVC column.  Install insulation into the PVC column and push down onto the top

of the water valve.

7. Mount the fountain onto the anchor bolts. Level and shim fountain as required.

8. Connect the drain line, water line and air control lines.  Excess lengths should be trimmed from the tubing. The water supply line must be

positioned for positive drain back out of the fountain and down through the water valve.  

Any water allowed to be trapped above the frost line will

freeze leaving the unit inoperable.

  Do not pull up on the connection lines as this could raise the valve above the frost line.

9. Check for proper operation by using fountain push button.  If the valve does not work properly check for leaks or kinks in the air control line.

10. After insuring proper operation reassemble fountain.  Installation of your fountain is now complete.

SITE PREPARATION DETAIL

FIG. 2

Содержание 4590

Страница 1: ...OF ELECTRICAL EQUIPMENT SUCH AS TELEPHONE COMPUTERS ETC TO WATER LINES IS A COMMON PROCEDURE THIS GROUNDING MAY BE IN THE BUILDING OR MAY OCCURAWAY FROM THE BUILDING THIS GROUNDING CAN CAUSE ELECTRIC...

Страница 2: ...cap may be removed for servicing the valve 5 We recommend that the top of the column be flush or slightly above the top height of the concrete pad 6 You should test the unit before you backfill Simply...

Страница 3: ...E BOTTOM COVER C 1 PVC DRAIN D PRESSURE FITTING 1 1 4 x 3 4 E CONNECTOR 1 1 4 TO 1 1 4 F 1 1 4 DRAIN TUBE G AIR CONTROL LINE H 1 4 WATER LINE J CONNECTOR FOR AIR CONTROL LINE SITE PREPARATION DETAIL F...

Страница 4: ...STALLING 97243C SINGLE VALVE CONTROL ASSY 1 Prepare trench for water supply and waste drain lines if required by local codes The hole should be deep enough to accommodate the PVC column and 5 cubic fe...

Страница 5: ...Gasket Clamp Hose Drain Gasket Bubbler Tube Assy Set Screw 8 32 x 125 Socket Head Screw 10 24 x 75 Strainer Plate Basin Bubbler Push Button Actuator Drain Tube Regulator Holder Pressure Fitting 1 1 4...

Страница 6: ...column to fit desired bury depth Set PVC column in excavating pit 2 Lay drain lines and water supply lines Provide service shut off valve for maintenance Flush the water supply line before attaching t...

Страница 7: ...PAGE 7 96812C Rev B 6 04 4590FR FTN SUGGESTED SITE PREPARATION DETAIL FOR THE 4590FR FTN WHEN USING THE SANITARYFR1 VALVE FIG 1...

Страница 8: ...TED SITE PREPARATION DETAIL FOR THE 4590FR FTN WHEN USING THE SANITARYFR1 VALVE 1 1 4 DRAIN TUBE SUPPLIEDWITHFTN 1 1 2 DRAIN TUBE SUPPLIEDBYINSTALLER Detail A LEGEND A ACCESS PANEL B REMOVABLE BOTTOM...

Страница 9: ...ert the 1 4 O D tube Label E into the 1 4 union provided with valve assembly Insert the 1 4 O D water line coming from the fountain into union Trim any excess length Step 4 Insert the 1 4 O D tube Lab...

Страница 10: ...PAGE 10 96812C Rev B 6 04 4590FR FTN Detail B 13 15 2 14 5 3 11 4 12 5 6 6 5 13 15 10 See Detail B FIG 4 FIG 5 Stream Height Adjustment...

Страница 11: ...1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 NS PARTNO Hex Nut 3 8 16 Single Valve Regulator Holder Regulator Nut Poly Tubing 1 4 Cut To Length To Bubbler Poly Tubing 1 8 Cut To Length To Actuator Canist...

Страница 12: ...ly hose coils into the bottom of the PVC column without any kinks and double check that the valve is positioned fully at the bottom of the PVC column Cap the PVC column Continuous Bubbler Flow Insure...