SAFE WORKING PRACTISE
A full risk assessment should be carried out prior to commencing the installation, which will be specific to the site
selected. The major risks associated with purely the assembly of this product are highlighted below, which can form
part of this overall assessment.
1.1
RISKS:
i)
Large parts which could be difficult to lift or handle.
ii)
Structure unstable until concrete footings have fully cured.
iii)
Parts at height that may require working overhead.
iv)
Heavy parts at height that require support during assembly
1.2
CONTROL MEASURES:
i)
Warn the public of the risk of injury, by placing signs and fencing the surrounding area, before commencing
installation.
ii)
All staff working on installation to wear suitable PPE including Toe Protective Shoes, Hard hat and Gloves.
iii)
Any staff or other persons on site, not working directly on the installation, to be kept away from the installation.
iv)
Ensure adequate personal and equipment are on site to handle and support the structure whilst it is being
assembled.
v)
Suitable working platform to provide secure access and provide support for parts required.
2
SPECIFICATIONS
SMP Playgrounds Ltd recommends an effective
Impact Absorbing Surface tested to EN1177 & BS7188
beneath this
play equipment. Refer to manufacturers instructions for details of installation. The surface should have a Critical Fall
Height greater than the Maximum Free Fall Height of the equipment.
Constructional Space is the approximate working area required to lay out and assemble the equipment.
For the safe operation of this equipment it must be installed on horizontal ground with the required minimum space.
The concrete foundations indicated are for average ground. Care should be taken concerning abnormal conditions.
If a loose fill surface is selected for this item it will require a very high level of maintenance to ensure a sufficient
thickness is in place at all times to provide ‘critical fall height’ protection.
3
PREPARATION
All equipment assembly and fixing must conform to EN1176.
Before commenceing the installation the surrounding area must be sufficiently fenced and signs erected to warn the
public of the risk of injury.
Tools / ancillary equipment:
I Mobile Platform, 10m tape measure, Spirit level, M6 & M10 Torx tool (Supplied with
unit), Torque wrench, Bolt cutters. Loose fill: Masking tape, Paint brush, Black paint.
ISSUE B 21-01-2013
Содержание nexus altitude nxa-03s
Страница 2: ...NEXUS ALTITUDE NXA 03S Page 2 ISSUE B 21 01 2013...
Страница 11: ...NEXUS ALTITUDE NXA 03S Section 1 Page 11 STEP 1 1 5 1 5 2800 34 47 43 31 X 3 ISSUE B 21 01 2013...
Страница 13: ...NEXUS ALTITUDE NXA 03S Section 1 Page 13 32 47 34 45 43 6 C D 37 11 ISSUE B 21 01 2013...
Страница 17: ...NEXUS ALTITUDE NXA 03S Section 1 Page 17 8 STEP 6 45 36 36 45 8 ISSUE B 21 01 2013...
Страница 19: ...NEXUS ALTITUDE NXA 03S Section 1 Page 19 4 STEP 8 1830 2284 1400 2187 0 0 310 400 90 26 X 2 ISSUE B 21 01 2013...
Страница 20: ...NEXUS ALTITUDE NXA 03S Section 1 Page 20 STEP 9 30 25 25 0 0 25 0 0 30 ISSUE B 21 01 2013...
Страница 21: ...NEXUS ALTITUDE NXA 03S Section 1 Page 21 STEP 10 42 46 37 20 M10 x 25 45 19 ISSUE B 21 01 2013...
Страница 22: ...NEXUS ALTITUDE NXA 03S Section 1 Page 22 STEP 11 18 35 45 18 35 45 ISSUE B 21 01 2013...
Страница 24: ...NEXUS ALTITUDE NXA 03S Section 1 Page 24 x 7 33 47 29 M10 x 65 STEP 13 42 46 35 28 47 x 5 ISSUE B 21 01 2013...
Страница 25: ...NEXUS ALTITUDE NXA 03S Section 1 Page 25 STEP 14 TYP 48 ISSUE B 21 01 2013...
Страница 26: ...NEXUS ALTITUDE NXA 03S Section 1 Page 26 ISSUE B 21 01 2013...
Страница 34: ...NEXUS ALTITUDE NXA 03S Appendix A Page 34 ISSUE B 21 01 2013...