Section 2 Commissioning checklist
Use the checklist that follows to complete the PROFINET or EtherNet/IP installation and
configuration procedure. Do the tasks in the order given.
Task
Completed
on page 7—Make all of the necessary hardware connection
(wiring).
on page 8 on the controller
Install the configuration file
on page 9 on the PLC environment.
• PROFINET—GSDML file
• EtherNet/IP—ESD file
on page 27 (PROFINET or EtherNet/IP) on the controller.
Section 3 Installation
D A N G E R
Multiple hazards. Only qualified personnel must conduct the tasks described in this
section of the document.
3.1 Install the module
D A N G E R
Electrocution hazard. Always remove power to the instrument before making electrical
connections.
Make sure that the PROFINET or EtherNet/IP module is installed in the controller. Refer to the
documentation supplied with the module
1
.
Notes:
• Make sure that the controller is compatible with the module. Contact technical support.
• Connect the module to the third slot on the right side of controller. Refer to
.
1
The module is factory installed based on the controller configuration.
English
5
Содержание SC4500
Страница 1: ...DOC343 52 90752 PROFINET and EtherNet IP modules 11 2021 Edition 2 User manual...
Страница 2: ......
Страница 4: ...Table of Contents 2...
Страница 6: ...Figure 1 Chain topology Figure 2 Star topology Figure 3 Ring topology 4 English...
Страница 26: ...16 Select the option Go Online 17 Select Download 24 English...
Страница 46: ...44 English...
Страница 47: ......