background image

GSSIM Mini Scaffolding Assembly & Operating Instructions

 

F. 

Tie continuous (running) scaffolds to the wall or structure at each end and at least every 30 feet of length in between when scaffold height 
exceeds the maximum allowable free standing dimension. Install additional ties on taller scaffolds as follows: 
On scaffolds 3 feet or narrower in width, subsequent vertical ties shall be repeated at intervals no greater than every 20 feet. On scaffolds 
wider than 3 feet, subsequent vertical ties shall be repeated at intervals no greater than 26 feet. The top tie shall be installed as close to the 
top of the platform as possible; however, no lower from the top than 4 times the scaffold’s minimum base dimension. Ties must prevent the 
scaffold from tipping either into or away from the structure.  Stabilize circular or irregular scaffolds in such a manner that the completed 
scaffold is secure from tipping.  Place ties near horizontal members.  
When scaffolds are fully or partially enclosed, or when scaffolds are subjected to overturning loads, additional ties may be required. Consult a 
qualified person.  

G. 

Do not erect scaffolds near electrical power lines. Consult a qualified person for advice.  

H. 

Access shall be provided to all platforms. Do not climb cross braces or diagonal braces.  

I. 

Provide a guardrail system, fall protection and toeboards where required by the prevailing code.  

J. 

Brackets and cantilevered platforms.  

1.    Brackets for system scaffold shall be installed and used in accordance with manufacturer’s recommendations. 

2.

 

Brackets for frame scaffolds shall be seated correctly with side bracket parallel to the frames and end brackets at 90 degrees to the   

        frames. Brackets shall not be bent or twisted from normal position. Brackets (except mobile brackets designed to carry materials) are to 

        be used as work platforms only and shall not be used for storage of material or equipment.  

3.    Cantilevered platforms shall be designed, installed and used in accordance with the manufacturer’s recommendations. 

 
K.            All scaffolding components shall be installed and used in accordance with the manufacturers’ recommended procedure.  Components shall not 
                be altered.  Scaffold frames and their components manufactured by different companies shall not be intermixed, unless the component parts 
                readily fit together and the resulting scaffold’s structural integrity is maintained by the user.   
L.            Planking – 

1. 

Working platforms shall cover scaffold bearer as completely as possible.  Only scaffold grade wood planking, or fabricated planking and 
decking meeting scaffold use requirements shall be used.  Planks and platforms should rest on bearers only. 

2. 

Check each plank prior to use to be sure plank is not warped, damaged, or otherwise unsafe. 

3. 

Planking shall have at least 12” overlap and extend 6” beyond center of support, or be cleated or restrained at both ends to prevent 
sliding off supports. 

4. 

Solid sawn lumber, LVL (laminated veneer lumber) or fabricated scaffold planks and platforms (unless cleated or restrained) shall extend 
over their end supports not less thank 6” nor more than 18”.  This overhang should be guardrailed to prevent access. 

M.          For “Putlogs” and “Trusses” the following additional guidelines apply: 

1. 

Do not cantilever or extend putlogs/trusses as side brackets without thorough consideration of loads to be applied. 

2. 

Install and brace putlogs and trusses in accordance with manufacturer’s instructions. 

N.          For rolling scaffolds the following additional guidelines apply: 

1. 

Riding a scaffold is very hazardous!  The SSFI and the SIA do not recommend nor encourage this practice. 

2. 

Casters with plain stems shall be attached to the frames or adjustment screws by pins or opther suitable means. 

3. 

No more than 12 inches of the screw jack shall extend between the bottom of the adjusting nut and the top of the caster. 

4. 

Wheels or casters shall be locked to prevent caster rotation and scaffold movement when scaffold is in use. 

5. 

Joints shall be restrained from separation. 

6. 

Use horizontal diagonal bracing near the bottom and at 20 foot intervals measured from the rolling surface. 

7. 

Do not use brackets or other platform extensions without compensating for the overturning effect. 

8. 

The top platform height as measured from the rolling surface of a rolling scaffold must not exceed four (4) times the smallest base 
dimension (CAL/OSHA and some government agencies require a stricter ratio or 3:1) 

9. 

Cleat or secure all planks. 

10.  Secure or remove all materials and equipment from platform before moving. 
11.  Do not attempt to move a rolling scaffold without sufficient help – watch out for holes in floor and overhead obstructions – stabilize 

against tipping. 

O.         Safe use of Scaffold – 

1. 

Prior to use, inspect scaffold to insure it has not been altered and is in safe working condition. 

2. 

Erected scaffold and platforms should be inspected continuously by those using them. 

3. 

Exercise caution when entering or leaving a work platform. 

4. 

Do not overload scaffold.  Follow manufacturer’s safe working load recommendations. 

5. 

Do not jump onto planks or platforms. 

6. 

DO NOT USE ladders or makeshift devices to increase the working height of a scaffold.  Do not plank guardrails to increase the height of 
a scaffold. 

7. 

Climb in access areas only and use both hands. 

III.        When Dismantling Scaffolding, The Following Additional Guidelines Apply: 

A.        Check to assure scaffolding has not been structurally altered in a way which would make it unsafe and, if it has, reconstruct and/or stabilize 
            where necessary before commencing with dismantling procedures. This includes all scaffold ties. 
B.         Visually inspect planks prior to dismantling to be sure they are safe. 
C.        Do not remove a scaffold component without considering the effect of that removal. 
D.        Do not accumulate excess components or equipment on the level being dismantled. 
E.        Do not remove ties until scaffold above has been dismantled to that level. 
F.         Lower dismantled components in an orderly manner.  Do not throw off of scaffold. 
G.        Dismantled equipment should be stockpiled in an orderly manner. 
 
 
 
 
201707 
 

 

Содержание Mini Scaffold

Страница 1: ...de to ensure the accuracy of this manual We reserve the right to change this product at any time without prior notice STOP DO NOT RETURN THIS PRODUCT TO THE RETAILER Questions Problems CONTACT CUSTOMER SERVICE If you experience a problem or need parts for this product visit our website http www buffalotools com or call our customer help line at 1 636 532 9888 Monday Friday 8 AM 4 PM Central Time A...

Страница 2: ...ath Erectors dismantlers and users of Multi Use Scaffold must read and fully understand these Safety Rules and Instructions MAXIMUM LOAD CAPACITY 500 Lbs Workers Materials DO NOT OVERLOAD SCAFFOLD IT MAY RESULT IN SERIOUS INJURY DO NOT STACK MORE THAN TWO UNITS HIGH OUTRIGGERS REQUIRED WHEN STACKING SPECIFICATIONS Assembled Product Dimension 46 45 H x 43 L x 21 D Platform Dimension 40 x 21 25 Adju...

Страница 3: ...of side brace B around leg of frame A at desired platform height Release lock pin and be sure that pin fully engages into hole in frame A leg Pin Is Disengaged Unlocked Position Pin Is Fully Engaged Locked Position STEP 2 Attach second side brace B to both frames A REPEAT INSTRUCTIONS IN STEP 1 All four L shaped lock pins must be inserted fully in holes on frame FIGURE C WARNING Be certain Pin is ...

Страница 4: ... WARNING RECHECK ALL SIDE BRACE LOCK PINS AND ALL CONNECTOR PINS FOR FULL ENGAGEMENT BEFORE ACCESSING PLATFORM RECHECK PLATFORM TO BE SURE IT IS PROPERLY SEATED WITHIN SIDE BRACE CHANNEL AND THE PLATFORM CLIPS ARE FULLY ENGAGED WHEN ACCESSING PLATFORM CLIMB OVER TOP OF FRAME LADDER DO NOT SWING AROUND SIDE OF FRAME REMOVE THE PLATFORM BEFORE ADJUSTING THE DECK LEVEL TYPICAL APPLICATIONS INCLUDE Pa...

Страница 5: ...OUS INJURY OR DEATH MAY RESULT FROM IMPROPER ERECTION OR USE of scaffolding equipment Erectors and users must be familiar with and follow safe practice and the Safety Rules contained herein These Safety Rules cover generalized situations only and should not be used to replace any other additional safety and precautionary measures that may be necessary to cover the many usual or unusual conditions ...

Страница 6: ...tability and safety of the scaffold Assure that the structure to which the scaffold is tied or anchored is capable of safely supporting all loads imposed by the scaffold L FREE STANDING SCAFFOLDS other than wall scaffolds must be restrained from tipping by guying or other means recognizing that stability is essential to the safety of the scaffold M NEVER USE LADDERS OR MAKESHIFT DEVICES on top of ...

Страница 7: ... equipment before using Never use any equipment that is damaged or defective in any way Mark it or tag it as defective Remove it from the job site E Scaffolds must be erected in accordance with design and or manufacturer s recommendations F Do not erect dismantle or alter a scaffold unless under the supervision of a competent person G Do not abuse or misuse the scaffold equipment H Erected scaffol...

Страница 8: ...ated veneer lumber or fabricated scaffold planks and platforms unless cleated or restrained shall extend over their end supports not less thank 6 nor more than 18 This overhang should be guardrailed to prevent access M For Putlogs and Trusses the following additional guidelines apply 1 Do not cantilever or extend putlogs trusses as side brackets without thorough consideration of loads to be applie...

Отзывы: