Multi - Module Dryer Stacking
3. Module Preparation and Installation
Setting Upper Module in Place
11. Once the upper module is in place over the lower module, slowly start to lower the upper module.
Make sure that the frame tie downs (D61-0011) come down to the outside of the module support
pads to which they will be bolted. Notice that the connecting section end (factory installed) has a
tab that extends below module frame. This tab will slide into the lower module just behind the
plenum end panel.
Figure 3P
12. When the upper module is set in place and the crane is bearing none of the weight, check to be
sure the upper module is level. If the upper module is not level place module support shims
(D61-0089) on the module support pads. It may be necessary to raise the upper module slightly
to place these shims.
Figure 3Q
Shim here
(If required)
Module support pad
Frame tie down
Shim here
(If required)
Tab of connecting
section end
Plenum end panel