42' Install Manual 6&11-W1 Snowshed Doorway Installation
Revised: 02/15/2022
25
26
27
Siding Door Fronts
Taping Ridge and Joints
The Door Front panels are sent wide and will need
to be trimmed in field with a plywood blade. Attach
siding Door Fronts. Use 1-1/4" ss screws.
Tape the ridge and joints where the door glazing
meets the dome. Clean surfaces to be taped with
isopropyl alcohol and allow to dry. Use 2-1/2" joint
sealing aircraft tape and make sure to use a roller on
the tape once it's on the dome. It needs to be above
60°F and dry. During the winter months, it is advisable
to use a hairdryer to warm the seams and tape.
(Taping tips available elsewhere in the installation
instructions).
Trim
this
edge
Tape
Tape
Tape
Trim Strips and Lower Pentagon Bottom Caps
Last
bottom
cap
Attach the last Vertical Trim Strips between wall
sections. Finish attaching the Horizontal Trim Strip.
Trim so it ends at edge of siding Door Front. Attach last
17" (with holes) Bottom Caps (sent long, trim to fit using
tin snips). Then attach the bottom of the panel through
the horizontal metal trim strip to the top of the wall
section using 1-1/2" ss screws. To finish installing the
second door, repeat steps 11 through 27.
Last
vertical
trim
strip
11 of 12