ATTACHMENTS
GRAVEL SPREADER ATTACHMENT #330 500
DUMP TRAY ATTACHMENT #330 700
55 GAL INSULATED TANK #145 500
(A)
#330 100 CHANNELS
(B)
#144 101 RODS
Install channel irons, tank and rods as shown in Fig. 7
(Refer to operation section on use of hot tanks)
Fig. 5
Gravel spreader
Fig. 6
Dump tray (or felt & insulation carrier)
Fig. 7
Hot stuff tank attachment
Wrenches are required for installation. Install gravel
spreader as shown in fig. 5. Shaft ends of spreader
drop into mount brackets on the frame. To install
handle and linkage, first attach linkage to dispenser and
then connect the other end with handle and secure with
bolt and nut provided. Clockwise adjustment of the
screw will make dispenser door open less; counter-
clockwise makes door open more. Yoke assembly on
back of dispenser is preset to proper door tension. If
more tension is needed for door closure, remove the
bolt and nut on the yoke and tighten as needed.
Install dump tray as shown in fig. 6. Shaft ends drop
into mount brackets on sides of power unit. Hopper
is self-locking: releases with lever to right of engine
cover