GREE Duct type Ducted Type Split Air-Conditioner Units
57
1 Engineering Installation Preparation and Notice
1.1 Installation Notice
Personnel and property safety are highly concerned during the entire installation process.
Installation implementation must abide by relevant national safety regulations to ensure personnel and
property safety.
All personnel involved in the installation must attend safety education courses and pass
corresponding safety examinations before installation.Only qualified personnel can attend the
installation. Relevant personnel must be held responsible for any violation of the regulation.
1.2 Installation Key Points and Importance
The system use refrigerant, instead of other agent, to directly evaporate to carry out the system heat.
High level of pipe cleanness and dryness is required in the system. Since various pipes need to be
prepared and laid out onsite, carelessness or maloperation during installation may leave impurities,
water, or dust inside refrigerant pipes. If the design fails to meet the requirement, various problems may
occur in the system or even lead to system breakdown.
Once the unit is energized and turned on for the first time, the display tube of outdoor unit displays
“A0”, which indicates debugging standby status. At this time, hold SW3 button successively for 5s on the
main module to enter into the automatic debugging, and then the engineering debugging will perform
according to the set procedures. Step 3 (conformation of outdoor unit’ quantity) and step 4
(conformation of indoor unit’ quantity) should be confirmed manually by pressing “SW3”, while other
procedures will be performed automatically. Once the debugging for each step is finished, “oC” will be
displayed; once all engineering debugging are finished, “oF” will be displayed, which indicates the unit is
under standby status.
2 Installation Materials Selection
The materials, equipment and instruments used during air conditioning engineering construction
must have certifications and test reports.Products with fireproof requirements must be provided with
fireproof inspection certificates and must meet national and relevant compulsory standards.If
environmentally-friendly materials are to be used as required by customers, all such materials must
meet national environmental protection requirement and be provided with relevant certificates.
2.1 Refrigerant Piping
(1) Material requirement: Dephosphorization drawing copper pipe for air conditioners.
(2) Appearance requirement: The inner and outer surface of pipe should be smooth without pinhole,
crack, peeling, blister, inclusion, copper powder, carbon deposition, rust, dirt or severe oxide
film, and without obvious scratch, pit, spot and other defects.
(3) Test report: Certifications and quality test reports must be provided.
(4) The tensile strength must be at least 240 kgf/mm².
(5) Specifications requirement.
Содержание UM600PH/A-M
Страница 4: ...4 PRODUCT...
Страница 9: ...GREE Duct type Ducted Type Split Air Conditioner Units 9 CONTROL...
Страница 25: ...GREE Duct type Ducted Type Split Air Conditioner Units 25 2 Click Next...
Страница 36: ...GREE Duct type Ducted Type Split Air Conditioner Units 36 3 Select language 4 Select system of units...
Страница 49: ...GREE Duct type Ducted Type Split Air Conditioner Units 49...
Страница 56: ...GREE Duct type Ducted Type Split Air Conditioner Units 56 INSTALLATION...
Страница 72: ...GREE Duct type Ducted Type Split Air Conditioner Units 72 DEBUGGING MAINTENANCE...
Страница 116: ...GREE Duct type Ducted Type Split Air Conditioner Units 116 UMLD400W A M P...
Страница 117: ...GREE Duct type Ducted Type Split Air Conditioner Units 117 UML500H A M P UML600H A M P UMD400PH A M P...
Страница 118: ...GREE Duct type Ducted Type Split Air Conditioner Units 118 UM500PH A M P UM600PH A M P...
Страница 121: ...JF00303352 JF00304250...