MAINTENANCE MANUAL OF GW4D20/GW4D20B TURBOCHARGED DIESEL ENGINES
420
Great Wall Baoding Internal Combustion Engine
Manufacturing Company Limited
2. Thermostat
Fig. 7-2-16 Removal and Installation orders of thermostat
Fig. 7-2-17 Removing the earthing cables of
storage battery
Removal
Preparation
(1) Disconnect the earthing cabled of storage battery.
See Fig. 7-2-17.
(2) Prepare a standby container for collecting the
discarded coolant, since the coolant is poisonous.
Properly dispose of the discarded coolant so as to
protect the environment.
(3) Remove the drain plug on cylinder body and drain
the coolant from the cooling system.
Warning:
when removing the drain plug to drain
away the coolant, take special care to avoid being
burnt by the machine body or coolant.
Removal order
①
Water inlet pipe
②
Thermostat cap
③
Thermostat assembly
④
Thermostat shield
Installation order
Install them in the opposite order of removal.