www.graf.info
17 / 40
4.
Fitting the set-up kit
4.8
Inlet baffle in final sedimentation
The supply pipe from the bio chamber to the final
sedimentation is fitted on an inlet baffle. This consists of a
DN 100 T-piece and a DN 100 pipe and is screwed on to the
dividing wall with two pipe clamps.
4.9
Overflow baffle on dividing wall
The overflow on the dividing wall in the final sedimentation is
accomplished with a T-piece and a downpipe in DN 70. The
position of the overflow is shown in section 4.1.
A DN 70 lip seal should be inserted in the drilled aperture.
The short DN 70 HT pipe is guided by the lip seal and the T-
piece can then be fitted on top of this on the side of the
second chamber. The T-piece should be extended
downwards with the longer DN 70 HT pipe.
Supply from
bio chamber