GPS GPS-DM48-AC Скачать руководство пользователя страница 2

C

hecklist |

 

GPS-DM48-AC

1.

Viewing through the clear housing faceplate, confirm the electrical wires are routed through the appropriate

conduit and the conduit is secured to the GPS-DM48-AC main housing

2.

Confirm the electrical connections are routed and wired in accordance with the installation manual

3.

Confirm the electrical wires are secured by the strain relief within the main housing and the terminal

connections are also secure

4.

Confirm the electrical supply is terminated in an appropriate fashion at the supply end and all local

and national electrical and building codes are complied with

5.

Use a soft cloth with isopropyl alcohol to wipe debris off the GPS-DM48-AC emitters

6.

Allow any residual alcohol to evaporate off the emitters

 prior to turning the ionizer on for the first time

ELECTRICAL INSTALLATION

STARTUP

UNIT STARTUP

1.

Power on the GPS-DM48-AC

2.

Confirm the GPS-DM48-AC is continuously powered and not configured to cycle with the HVAC duty

3.

Once powered on, confirm the green power LED is illuminated

4.

Confirm that the cleaning cycle frequency is set to 1 day as detailed in the IOM

5.

Confirm the clear faceplate is reattached and secured by the four provided fasteners

6.

Measure the voltage at the GPS-DM48-AC emitters (both polarities) and confirm it is above the minimum

target level of 3kV

7.

Visually confirm there is no du

s

t or dirt on the carbon fiber emitters after they were cleaned with isopropyl

alcohol during installation

8.

With the GPS-DM48-AC operational, verify ion density output. Confirm it meets the combined polarity target

of 200M ions/cc using the AIC2 ion meter ions/cc for each polarity measured 1” away with air handler

fan off (no airflow)

9.

Confirm the 

final configuration

 is securely attached to the duct wall

 and operational i

n accordance with the

installation manual