Gossen MetraWatt METRALINE RLO-CHECK Скачать руководство пользователя страница 1

 SWITCHING THE INSTRUMENT ON

 

 



(The METRALINE RLO-CHECK is switched off.) Press and hold 

the « 

ϕ 

» until you hear a double acoustic signal.

 

 

 

The display is activated. The METRALINE RLO-CHECK is ready 

for measurement. The last conducted balancing procedure is 

active. The acoustic signal is not suppressed.

 

 

 

 SWITCHING THE INSTRUMENT OFF

 

 



(The METRALINE RLO-CHECK is switched on.) Press and hold 

the « 

ϕ 

» key for at least 2 seconds.

 

 

 

 DEACTIVATING THE ACOUSTIC SIGNAL

 

 



(The acoustic signal is not suppressed.) Briefly press the « 

ϕ 

» key

 

 

The 

icon appears. The acoustic signal is deactivated  

(the acoustic signals for balancing and the voltage alarm remain 

activated). 

 ACTIVATING THE ACOUSTIC SIGNAL

 

 



(The acoustic signal is deactivated.) Briefly press the

 

« 

ϕ 

» key. 

 BALANCING RESISTANCE OF THE 

   ACCESSORIES

 

 



(The METRALINE RLO-CHECK is switched on). Connect the 

telescoping rod or the test probe to the measurement coil cable 
and connect the cable to the « 

Ω 

» terminal.  



Roll out the cable from the cable retractor and connect the end of 

the cable to the alligator clip or the PE adapter for electrical outlets.

 

 



Activate the balancing procedure by briefly pressing the « 

ϕ 

»

 

key 

twice. « 

0 Ω

 » is displayed.

 

 



Contact the end of the telescoping rod 

or 

the test probe with the

 alligator clip or 

the PE adapter for electrical outlets for 

several seconds.

 



Blue background, 0.00, two short acoustic signals 

followed by a continuous acoustic signal 

indicate that balancing has been successfully 
completed 

(

the displayed value may fluctuate 

due to measuring tolerance, for example 
between 0.00 and 0.07).

 

 

 

The METRALINE RLO-CHECK is ready for measurement. The 

results of this balancing procedure are retained until balancing is 
conducted again, even if the battery is replaced or the 

METRALINE RLO-CHECK is turned off

 

Red background, E01 and 0 

Ω  icon

:  

 

Balancing has not been successful (e.g. 

because resistance to be eliminated is too 

high or the alligator clip didn’t correctly 

contact the end of the telescoping rod 
etc.). Results of the previous balancing 

procedure remain active. Switch the 

METRALINE RLO-CHECK off.  

 

Ω

 

 

Ω

 

0.0

 

E0 

Ω

 

MEASURING PROTECTIVE CONDUCTOR 

  RESISTANCE IN THE INSTALLATION

 

:  

 



(

The

 METRALINE RLO-CHECK is switched on). Connect the 

telescoping rod or the test probe to a measurement coil cable 

and connect the cable to the « 

Ω 

»

 

terminal. 



Roll out the cable from the cable retractor and connect the end 
of the cable to the alligator clip or the PE adapter for electrical 

outlets. 



Connect the alligator clip or the PE adapter for electrical outlets 

with the selected equipotential bonding reference point (control 

panel, earth electrode, pin in an electrical outlet etc.). 



Contact the protective conductors located nearby with the 
telescoping rod or the test probe. 

Important note! 

If 

resistance of the accessories has not been balanced (see E), 

displayed resistance includes the accessories. 

 

One of the following displays appears: 

 

Red background, lightning bolt icon and 

brief acoustic signals: DANGER,

 

 

interference voltage.  
The interference voltage value is displayed.

 

 

 

Blue background and continuous acoustic 
signal:

 Resistance 

 1.00 

Ω, 

e. g. 0.64 

Ω

.  

 
 

Red background

 

:

  

Resistance between 1 

Ω 

and 20 

Ω,  

e. g. 3.28 

Ω

 

Ω

 

3.2

 

Ω

 

0.6

 BALANCING RESISTANCE OF THE  

  ACCESSORIES AT THE 2 TERMINALS : 

 



(The METRALINE RLO-CHECK is switched on). Connect the 

telescoping rod or the test probe to the measurement coil cable 

and connect the cable to the « 

Ω 

»

 

terminal

.

 



Connect a second test probe to a measurement cable and 

connect the cable to the « AUX » terminal. 



Briefly press the « 

ϕ 

» key twice.

 

« 

0 Ω

 » is displayed.

 

 



Contact both ends of the telescoping rod or the test probe 

for

 

several seconds. (While doing so, you can 

leave the alligator clip or the PE adapter for 

electrical outlets connected to the equi-
potential bonding reference measuring 

point).

 

 



Blue background, 0.00, two short acoustic signals 

followed by a continuous acoustic 

signal 

indicate

 

that balancing has been 

successfully completed (the displayed value 

may fluctuate due to measuring tolerance, 

for example between 0.00 and 0.07).

 

 

 

The METRALINE RLO-CHECK is ready for measurement. The 

results of this balancing procedure are retained until balancing is 

conducted again, even if the battery is replaced or the 
METRALINE RLO-CHECK is turned off. 

 

Red background, E01 and 0 

Ω 

icon

 

:  

Balancing has not been successful (e.g. because 
resistance to be eliminated is too high or the 
test probe didn’t correctly contact the

 

end

 

of 

the telescoping rod etc.). Results of the previous balancing 

procedure remain active. Switch the METRALINE RLO-CHECK 

off.

 

Switch the METRALINE RLO-CHECK off.

 

 

 

Ω

 

 

Ω

 

0.0

 

E0 

Ω

 

 

USING ONLY THE CABLE FROM THE 

   REEL COMBINED WITH AN ALTERNATIVE  

      MEASURING INSTRUMENT : 

 

During routine daily work, a simple extension is frequently required 
for connection to another measuring instrument. This is possible 

with the help of the « AUX » terminal. 

 



(The METRALINE RLO-CHECK is switched on). Undo all 

connections (terminals and role-up cable). 



Press and hold the « 

ϕ 

» key for at least 2 seconds in order to 

switch the device off. 



Connect the alternative measuring instrument to a measurement 

cable and connect the cable to the « AUX » terminal. 

 

The cable on the cable retractor is now available for use as an 
extension cable. 

The circuit set up in this way is protected by the internal fuse in the 

METRALINE RLO-CHECK.

 

 

The METRALINE RLO-CHECK must remain switched off and may 

never be switched on when an external measuring instrument is 
connected

.

 

 MEASURING PROTECTIVE CONDUCTOR  

   RESISTANCE OF A DEVICE NOT  

      CONNECTED TO THE CABLE REEL

 

:  

 



(

The

 METRALINE RLO-CHECK is switched on). Connect the 

telescoping rod or the test probe to the measurement coil cable 

and connect the cable to the « 

Ω 

»

 

terminal. 



(The cable from the cable retractor which is connected to the 

selected equipotential bonding reference point can remain 
connected.)

 

 



Connect an additional test probe to a further measurement 

cable and connect the cable to the « AUX » terminal. 



Contact all accessible metal parts (of the device which is not 

connected to the cable from the cable reel) and the protective 
conductor of the device plug. 

Important note! 

If resistance of 

the accessories has not been previously balanced (see G), the 

displayed resistance includes the accessories

 

.  

 
One of the following displays appears:

 

 

 

Red background, lightning bolt icon and 

brief acoustic signals: DANGER,

  

interference voltage.  

The interference voltage value is displayed. 

 

Blue background and continuous acoustic 
signal

 

:

 Resistance 

 1.00 

Ω, 

e. g. 0.64 

Ω

.  

 

Red background:

 

Resistance between 1 

Ω 

and 20 

Ω,  

e. g. 6.90 

Ω

 

Ω

 

6.9

 

Ω

 

0.3

3-447-019-03 

1/6.18 

OPERATING INSTRUCTIONS 1/2 

METRALINE RLO-CHECK 

Digital, low resistance measuring  
instrument per EN 61557-4 / VDE 0413-4  

with cable reel and 30 m cable for measuring 
the resistance of protective conductors and 
equipotential bonding conductors 

CONDENSED INSTRUCTIONS:

 

 

 

Belt: 

Lay the belt around your waist and adjust it. 

 

«

Ω

»

 terminal: 

Connect the measurement coil cable 

to this terminal. This in turn must be connected to a 
telescoping rod or a test probe.  

 

4 mm banana plug: 

Connect an alligator clip or a 

PE adapter for electrical outlets to this plug  
 

«

ϕ

»

 key: 

Press and hold this key until you hear a 

double acoustic signal.  

 

Alligator clip or PE adapter for electrical 

outlets: 

Connect this (these) to the selected equipotential 
bonding reference measurement point (e.g. the 

ground pin of an electrical outlet).  
 

Test probe or telescoping rod: 

Connect this/

these to the protective conductor.  
 

Display: 

Read resistance (in ohms) which was 

measured between the alligator clip (or the PE 

adapter for electrical outlets) and the test probe  
(or the telescoping rod).  

 

22

 

22

 

Subject to change without notice • PDF version available on the Internet

 

 

 
 
 

 

 

Phone  +49 911 8602-111

 

GMC-I Messtechnik GmbH  

 

Fax      +49 911 8602-777 

Südwestpark 15   

 

 

E-Mail  [email protected] 

90449 Nürnberg 

Germany  

www.gossenmetrawatt.com 

Содержание METRALINE RLO-CHECK

Страница 1: ...ed by a continuous acoustic signal indicate that balancing has been successfully completed the displayed value may fluctuate due to measuring tolerance for example between 0 00 and 0 07 The METRALINE RLO CHECK is ready for measurement The results of this balancing procedure are retained until balancing is conducted again even if the battery is replaced or the METRALINE RLO CHECK is turned off Red ...

Страница 2: ...s Approx 5 hours and 50 minutes for continuous measurement of volume resistance of an earthing conductor of less than 1 Ω with activated acoustic signal and new batteries The instrument is switched off automatically after five minutes of nonuse Conformity with standards EN IEC61010 1 2010 EN IEC61557 4 2007 Conformity with European directives 2011 65 EC RoHS directive 2006 95 EC low voltage direct...

Страница 3: ...r see I 0 5 A fuse protected Warning regarding interference voltage If interference voltage is applied to the protective conductors resistance measurement is disabled An intermittent acoustic signal is generated the color of the display is changed to red and the interference voltage value is displayed If a minus sign appears to the left of this value the interference voltage is direct voltage and ...

Страница 4: ...for at least 2 seconds in order to switch the device off Remove the 2 Ω calibration jumper M2 Replace the battery compartment lid J2 and retighten the screw J1 Press and hold the ϕ key until you hear a double acoustic signal in order to switch the device back on again Balance resistance to your accessories in accordance with section E or G The METRALINE RLO CHECK is ready for measurement Recalibra...

Отзывы: