Geovent MINI ARM Скачать руководство пользователя страница 5

5

2.1 Installation - ATEX application

This is only necessary, when the ATEX upgrade packa-

ge has been purchased.

The mini arm is based on the same components as the 

standard version, but there are some small alterations 

that needs to be followed correctly.

1)  The hose that is applied is the transparent hose (P2 

PU AS).

2)  The wire on the hose, is to be freed from the hose 

construction, so that you have app. 10-15 cm of wire, 

that can be moved  around.

3) Connect the loose end of the wire, as shown below.

4)  Connect the other end of the hose to ground, in order 

to make the arm antistatic (R8 <10 Ohm).

2.2 Mounting of optional equipment

Installation of damper

The MINI arm can be supplied with a damper. The dam-

per must be installed from the factory. Contact your de

-

aler.

2.2 Trial run – exact adjustment

After the final mounting, the MINI Arm should be adju

-

sted to the typical working area, for optimum utilization 

of the arm. Do so by adjusting the rotary joints mentio

-

ned in item 2 by means of 2 fixed spanners.

If there is a problem with the arms carrying ability, you 

can try to add more plate springs (black) to the joint, so 

that the arm can be tighten further.

The following guide gives you an idea about how tight 

each joint should be. Please note, this is only a guide, 

and may vary according to the actual installation and 

personal preferences.

Mini arm:    

M8

1,5m 

 

Wall bracket  

7,5 NM

 

Joint in the middle  

7,5 NM

 

Bracket at hood  

7 NM

2,0m 

 

Wall bracket  

9 NM

 

Joint in the middle  

9 NM

 

Bracket at hood  

7 NM

3.0 User instruction – application

For normal use, the arm is to be self-retentive in the re-

quired position within the working area. The bracket of 

the arm supplies a 360° rotary working area.

When moving the arm, remember to hold it in the requi-

red position for app. ½-1 second, so that the joint will 

lock up in the requested position (do not push the arm 

into position).

If the equipment has been correctly dimensioned, the 

funnel of the arm should be placed in vertical position 

300-500 mm over the point of pollution.

Thus up to 99% of the polluting particles will be caught.

Optimal situation:

Less optimal situation: