7.1 Preparation
7.2
Work to be carried out
7
|
Maintenance
To avoid system-related problems, the following service work must be carried out on the Plusbox:
Cleaning: A dirty condenser leads to performance losses!
Visual inspections and possible condenser cleaning therefore required on a monthly base.
- Prior to cleaning, mask the ventilation apertures between condenser/fan and machine room and
then remove again before subsequent start-up
Neither dirt nor moisture are allowed to penetrate the machine room.
- We recommend using compressed air and a soft brush for cleaning.
Further maintenance work in accordance with the instructions for assembly on the compressor.
WARNING
Before starting any work on the compressor:
Switch off the compressor and secure it to prevent a restart.
Relieve compressor of system pressure.
Prevent air from infiltrating the system!
After maintenance has been performed:
Connect safety switch.
Evacuate compressor.
Release switch-on lock.