background image

General

These instructions apply to the following catalog numbers:

• Circuit breaker modules AMC6FGB or AMC4FGB.
• Circuit breaker frames FGN, FGH, FGL, or FGP

Installation

1. Phase balancing for two-pole devices on three-phase

systems.

Reposition the bus clip assembly from A or C

phase to B phase, as shown in Figures 1 and 2.

Remove the screws in the bus clip assembly and move

the bus clip to the B-phase position. Fasten the bus

clip assembly in the new location with the slotted

hex-head SEMS screws provided and tighten to 27–

32 in-lb.

Figure 1. Repositioning the bus clip assembly.

Figure 1. Repositionnement de l’assemblage de la pince de barre

omnibus.

2. Prepare the breaker module (for two breakers only).

Before installing the breakers on the module, remove
the tinnermans and barriers, as shown in Figures 3

and 4.

3. Install the circuit breaker(s).

Place the Belleville

washers and hex-head screws into the line straps of

the circuit breaker, as shown in Figure 5. Position the

ON side of the breaker on the module, as shown in
Figure 5. Align the hex-head screws in the stud-post

holes and tighten to 90–110 in-lb. Fasten the OFF

side of the breaker to the mounting brackets with the
round-head screws and flat washers and tighten to

27–32 in-lb. Repeat the procedure for a second

breaker.

Généralités

Ces instructions s’appliquent aux numéros de catalogue

suivants:

• Modules de disjoncteurs AMC6FGB ou AMC4FGB.
• Cadres de disjoncteurs FGN, FGH, FGL, ou FGP

Installation

1. Équilibrage de phase pour mécanismes deux-pôles

sur systèmes trois-phases.

Repositionner l’assemblage

de la pince de barre omnibus de phase A ou C à

phase B, tel qu’illustré aux Figures 1 et 2. Retirer les

vis dans l’assemblage de barre omnibus et déplacer la

pince de barre omnibus à la position phase B. Fixer

l’assemblage de barre omnibus dans son nouvel

emplacement avec deux vis rainurées à tête

hexagonales SEMS fournies et serrer à 27–32 lb.-po.

Figure 2. Repositioning the bus clip to balance the load.

Figure 2. Repositionner la pince de barre omnibus pour équilibrer la

charge.

2. Préparer le module du disjoncteur (pour deux

disjoncteurs uniquement).

Avant d’installer les

disjoncteurs sur le module, retirer les tinnermans et

les barrières, tel que montré aux Figures 3 et 4.

g

Spectra Series

Power Panelboards

Panneaux de distribution Spectra Series

Circuit Breakers and Modules
Disjoncteurs et Modules

DEH40420

Installation Instructions

R02

Instructions d’installation

DEH40419

Installation Instructions

R03

Instructions d’installation

Screws and Bus Assembly

Assemblage des vis et de

la barre omnibus

SEMS Screws

Vis SEMS

A and C Phases

Phases A et C

B Phase
Phase B

A & C Phase

As Received

A & B Phase

B & C Phase

Phases A & C

telles que

reçues

Phases A & B

Phases B & C

Содержание Spectra Series AMC6FGB

Страница 1: ...r a second breaker Généralités Ces instructions s appliquent aux numéros de catalogue suivants Modules de disjoncteurs AMC6FGB ou AMC4FGB Cadres de disjoncteurs FGN FGH FGL ou FGP Installation 1 Équilibrage de phase pour mécanismes deux pôles sur systèmes trois phases Repositionner l assemblage de la pince de barre omnibus de phase A ou C à phase B tel qu illustré aux Figures 1 et 2 Retirer les vi...

Страница 2: ... module Figure 4 Preparing the breaker module for a two breaker installation Figure 4 Préparer le disjoncteur pour une installation deux disjoncteurs 3 Installer le ou les disjoncteurs Placer les rondelles Belleville et les vis à tête hexagonale dans les brides de ligne du disjoncteur tel que montré à la Figure 5 Positionner le côté ON du disjoncteur sur le module tel que montré à la Figure 5 Alig...

Страница 3: ...reakers Figure 8 Installation complétée avec deux disjoncteurs 5 Installer le module Rétracter complètement les loquets et accrocher un côté du module de disjoncteur au rail de l intérieur tel que montré à la Figure 9 Relâcher le loquet Pivoter le module sur les barres omnibus et engager le second loquet Relâcher le loquet Serrer les vis de loquet à 25 lb po tel que montré aux Figures 9 et 10 Figu...

Страница 4: ... calibrage These instructions do not cover all details or variations in equipment nor do they provide for every possible contingency that may be met in connection with installation operation or maintenance Should further information be desired or should particular problems arise that are not covered sufficiently for the purchaser s purposes the matter should be referred to the GE Company g GE Cons...

Отзывы: