Section 3.0 - Delivery Procedure
Section 3.0 Delivery Procedure
3.1
System Transportation - Temperature Extremes
When transporting the CT system, ensure that the system is not exposed to temperatures or
humidity outside the following specifications.
Temperature: -40º to +158º F (-40º to +70º C)
Humidity: 10% to 100%
NOTICE
Component Freezing occurs if CT system is exposed to temperatures below 0º F (-18º C) for
a period longer than two days.
Allow a minimum of 12 hours for the CT system to adjust to ambient room temperature prior
to installation.
Inspect for visible condensation and allow all moisture to evaporate before starting the
installation.
3.2
Stored Systems
If your system was stored for more than three months:
•
Complete a visual inspection, looking for damage due to improper storage.
•
Check for the latest software revisions, options, and component changes.
•
Contact the OLC for support.
•
Movers are required to move the equipment to the scan room.
3.3
Construction Site Storage
When storing the CT system at a construction site, be sure to adhere to the following storage
requirements:
•
Construction site packaging must be ordered and the system shipped packaged for storage.
•
Do not damage or puncture the shipping crate.
•
Do not remove packaging until the completion of all construction at the site and the removal of
all dust created by the construction.
•
Maintain a storage temperature within the range of 10º to 32º C (50º to 90º F).
•
Maintain a relative humidity (non-condensing) between 20% and 70%.
3.4
Construction Site Installations
A construction installation describes installations at sites without an occupancy permit, or ongoing
construction. In general, construction sites fail to meet the required specifications for system
delivery, and GE Healthcare does not recommend such installations, as they can result in delays,
increased costs, and possible damage to the system. When construction-site delivery proves
unavoidable, the installation falls into one of two categories:
•
Full construction site with completed radiology area.
•
Full construction site with limited delivery access.
Review these categories to determine which most closely matches the condition of the planned
installation site.