Lockout/Tagout (LOTO) Requirements
Follow OSHA Lockout/Tagout requirements (USA) or local Lockout/Tagout requirements by ensuring
you are in total control of the AC power plug at all times during the service process. This will protect
service personnel from injuries caused by unexpected energizing or start-up of equipment during
service, repair, or maintenance.
To apply Lockout/Tagout (LOTO):
1.) Plan and prepare for shutdown.
2.) Shutdown the equipment.
3.) Isolate the equipment.
4.) Apply Lockout/Tagout Devices.
5.) Control all stored and residual energy.
6.) Verify isolation.
All potentially hazardous stored or residual energy is relieved.
WARNING
WARNING
ENERGY CONTROL AND POWER LOCKOUT FOR VENUE™.
WHEN SERVICING PARTS OF THE SYSTEM WHERE THERE IS EXPOSURE TO
VOLTAGE GREATER THAN 30 VOLTS:
1) Follow LOCK OUT/TAG OUT procedures
2) TURN OFF THE BREAKER.
3.) UNPLUG THE SYSTEM.
4.) MAINTAIN CONTROL OF THE SYSTEM POWER PLUG.
5.) WAIT FOR AT LEAST 30 SECONDS FOR CAPACITORS TO DISCHARGE AS
THERE ARE NO TEST POINTS TO VERIFY ISOLATION. THE AMBER LIGHT
ON THE OP PANEL ON/OFF BUTTON WILL TURN OFF.
6.) BEWARE THAT THE MAIN POWER SUPPLY AND BACK END PROCESSOR
MAY BE ENERGIZED EVEN IF THE POWER IS TURNED OFF WHEN THE
CORD IS STILL PLUGGED INTO THE AC OUTLET
7.) Remove/disconnect the battery if present
Ultrasound System components may be energized.
Capacitors on Ultrasound Systems with the Shearwave Option can take up to 5
minutes to discharge.