GE
Direction 5370626-100, Revision 18 LOGIQ e/LOGIQ e Vet/LOGIQ i/Vivid e Basic Service Manual
Chapter 4 Functional Checks
4-3
When power is applied to the scanner, power is distributed to the Cooling Unit, Control Panel, LCD,
Peripherals and the Back-end Processor.
4-3-1-2
Turn on the system
Press the
Power On/Off
switch at the front of the system once.
When the
Power On/Off
switch on the Control Panel is pressed once, the Back-end Processor starts
and the software code is distributed to initiate the scanner.
No status messages are displayed during this process.
4-3-2
Power Off/ Shutdown
NOTE:
After turning off a system, wait at least ten seconds before turning it on again. The system may not be
able to boot if power is recycled too quickly.
4-3-2-1
Back-end Processor Power Down
To power down the system:
1.) Press the
Power On/Off
switch at the front of the system once.
2.) The System-Exit window is displayed.
3.) Using the Trackball or Select
key, select Shutdown.
Figure 4-33 Power On/Off Switch
Figure 4-1 System Exit Window
Power On/Off
switch