LCA
RG66000986 – Rev.00
8
INSTALLATION
INSTALLATION CLEARANCE REQUIREMENTS
It is of fundamental importance to ensure an adequate volume of air both on the intake and outlet sides
of the condenser coils; it is highly important to prevent the air delivered from being re-aspirated as this
may impair the performance of the unit or even cause an interruption in normal operation. For this
reason it is necessary to guarantee the following clearances (see figure on this page):
- rear side/plumbing connections: min. 1.5 metres to guarantee access to plumbing connections and/or
for any necessary maintenance on the pumps, reservoir, expansion tank and flow switch.
- electric control board side: min. 1.5 metres to guarantee access for inspection and/or maintenance of
cooling components
- coil side: min. 1.5 metres to ensure proper air circulation and access to the compressor compartment,
also from the side.
- top side: there must be no obstacle to expulsion.
1.5 m
1.5 m
1.5 m
1.5 m