Once both sides of elements are in place
and sitting in grooves, move to the back of
the furnace.
If you are having issues with getting the
elements to sit in the grooves, you can pin
elements back. If you do not have any
element pins then elements may fall into
place when elements are Annealing in the
first hour of start up. If they are still not
sitting correctly you will need to source
some element pins or use excess element
tails (see below) to make some element
pins.
REPLACING ASHING ELEMENTS
Slide ceramic tube back over the
element tails top and bottom.
Push into place, leaving about 5-10mm
out, and silicon around to keep in place.