Please Read Before Installing

Note:  The 703-400-01 model features a stainless steel containment tank. In the 

state of Florida, EBW approves the installation of the 703 spill container 
with the following instructions:

1.  Dig around the existing riser pipe to the desired depth.

2.  Clean the riser pipe to eliminate any sand, scalding or rust.

3.  Apply a layer of duct tape around the threads at the top of the riser pipe to pro-

tect the gasket.

4.  Slip the manhole assembly over the riser pipe to the approximate depth.

5.  Lubricate the pipe & gasket to allow the gasket to slide easily.  Slip the gasket 

over the riser pipe and position it in the clamp ring insert.

6.  Slip the clamp plate into position over the clamp ring and install the six 5/16" 

- 18 nuts, but DO NOT tighten them at this time.

7.  Position the spill containment at the proper height, back fi ll, and tighten the six 

nuts in the clamp ring.

8.  Remove the duct tape from the riser pipe, then install the tight fi ll adaptor and 

cap.

9.  Backfi ll area surrounding containment basin to sub-grade. Install concrete 

around spill containment manhole to required grade levels.

Note:  In the state of Florida the entire stainless steel containment needs to be 

encapsulated in concrete.

702/703 Spill  Containment

Installation Instructions

Check for Leaks

Every unit should be tested for leaks prior to, and after, pouring the concrete.  Fill the 
unit completely with water.  If the test water level drops at all within one hour, then a leak 
exists.

If the unit continues to leak, the entire spill container should be removed from the riser 
pipe and replaced with another.  RE-TEST.

After the concrete has been poured, RE-TEST to make sure that no damage occurred 
during installation.

Drawings on Reverse