NOTE:

 Make sure that the wires are connected tightly to the terminals. 

7. Put the terminal block cover back on the rear panel of the module.

5. Operation

Transfer from UPS to maintenance bypass mode

To manually change from UPS to maintenance bypass function, follow the steps included below:

Step 1: 

Press the 

OFF

 button of the UPS unit to transfer to bypass mode.

Step 2:

 Open the maintenance switch cover. If step 1 is not executed first, then the UPS unit will transfer to bypass mode automatically 

with the output control signal connection when opening the maintenance switch cover.

Step 3: 

Turn the switch to its 

BPS

 position and switch off the UPS input breaker on the bypass switch module. Every device will be 

directly fed from utility as the current flowing through  the UPS will be interrupted. The output and input terminals of the UPS are now 

isolated from the system. Ensure that the UPS is off, and that battery power is disconnected as well, with the terminals completely 

de-energized before performing any maintenance on the unit.

  

Transfer from maintenance bypass to UPS mode

After the system has been placed into service mode, it must be returned to UPS state to resume normal operation.   

Step 1: 

Switch the input breaker of the bypass switch module back on and reconnect the UPS battery power. This will cause the UPS 

to enter into bypass mode.

Step 2:

 Turn the maintenance switch to its 

UPS

 position. All loads will be then powered by utility power through the UPS bypass mode. 

Step 3:

 Close the maintenance switch cover and press the 

ON

 button of the UPS unit. At this stage, the connected equipment is again 

being powered and protected by the UPS.  

NOTE:

 If maintenance will be executed in a different location, follow the steps under 

Transfer from UPS to maintenance bypass 

mode

 before removing the power supply unit and the bypass switch module.

Step 4:

 Finish by disconnecting all the wires between the UPS and the bypass switch module for complete isolation.

6. Specification of critical components

Input breaker

Bypass switch

Input/output terminal

Current
Voltage
Current
Voltage
Current
Voltage

63A
250V
63A
690V
60A
600V

Parameter

Max.

Full installation with maintenance bypass and isolation transformer (110V or 220V operation)

MAINTENANCE

BYPASS

UPS

BATTERY PACK

ISO (output to load)

Full installation with maintenance bypass (220V operation only)

MAINTENANCE

BYPASS

(Output to load)

UPS

BATTERY PACK

Отзывы: