7.1.4 Conducting a trial run
After the machine is set up and prepared and before work begins, a trial run must be conducted in
unloaded condition
.
Objective
Check to ensure the machine is set up correctly and functioning properly.
Prerequisites
-
Machine is ready for operation
-
Machine is fully set up
Familiarise yourself with the basic safety instructions (see section 2) and the
instructions for first-time start-up (see section 5.1) before the trial run and take
all the safety precautions listed in these sections.
Procedure
-
Turn on the machine as specified
-
Perform all functions of the machine individually
7.1.5 Uncoupling the trailer
Follow the instructions in sections 7.1.1 to 0 in reverse order.