7. Commissioning
7.1 Initial commissioning
•
Document the commissioning procedure (actions and settings).
•
Check that the installation and other actions prior to use have been carried out in full (e.g. power supply available and
connected, functioning or active fuses, seal tightness of the equipment, transport protection of the volume sensor
removed).
Commissioning is preferably done via Flamconnect App
Caution:
Ensure that the basic vessel is not filled until all the commissioning measures have been completed.
•
Fill and de-aerate the heating or cooling system (not the vessel!)
•
Check the operational readiness of the top-up line.
•
Open the valve at the top-up connection and the lockshield valve at the flexible connection assembly (vessel connection).
•
SWITCH ON THE CONTROL UNIT and run the Commissioning procedure
(“7.2 Overview menu options” on page 29, Commissioning).
•
Follow the steps on the Flextronic controller to set up the MK Automat
Language selection
Time settings
Activate Bluetooth
Confirm manual is read
Select vessel (only 1 possible selection)
Level calibration (Vessel needs to be empty)
Select accessories
Confirm settings
•
This start-up procedure is followed by switching ON the top-up unit (optional, see installation example with FlamcoFill P).
•
In other cases the main vessel or all vessels are to be filled with a minimum water supply. The amount of water to be
filled should be according to chapter 7.2. This value covers water losses and decreased filling levels caused by deaeration
during operation. (Note the pressure difference between the available compressed air pressure and the flow pressure of
the filling equipment! see also instructions for re-filling).
•
Open the ball valve on the cold-leg entrainment (system connection)
•
Seal the lockshield valves.
•
The completion of all the tasks to be carried out, the review of technical data, recommendations and explanations in this
manual lead to the pressure expansion automat being ready for operation.