Electrical connection (230 VAC) (regarding figure 6):
Electrical work during installation and commissioning may only be carried out by professional electri-
cians. In principle, all work on the high-energy ignition system requires qualified professionals.
Before the electrical connection is established, the ignition lance must be guided into the combustion
chamber and secured. Make sure to observe the general safety instructions on page 4, then open the lid
of the casing. Check the individual wires of the power supply cable to ensure they are not live.
1.
Check and set power supply at the latching switch (see figure 7), 115 VAC or 230 VAC.
2.
Use BiHF(K)-J (or similar) as power supply cable.
3.
Insert the cable into the right-hand cable gland (marking 115/230 VAC)
4.
Wire connection for:
a.
Phase L1 to terminal L
b.
Neutral wire to terminal N
c.
Protective ground wire to terminal PE
d.
Power supply for ignition monitoring to terminal C
e.
Feedback ignition ON to terminal NO
f.
Feedback ignition OFF to terminal NC
5.
Pull the cable back, but not to the extent that the connected wires are under tension, tighten the
cable gland.
6.
Close the lid on the casing and perform a function test.
1 2
High voltage cable connection
(to the ignition electrode)
Electrical bonding connection
(earthing connection to the installation) Connection assignment
NO: Ignition monitoring / NO= Normally Open
C: Ignition monitoring / Common
NC: Ignition monitoring / NC= Normally Closed
L: Hot (Phase L1)
N: Neutral
PE: Protective Earth
Cable entry for supply voltage
(ignition ON)
FIGURE 4.
Electrical connection of high-energy ignition unit HE-PP-12