PREPARATION OF THE MACHINE
1.
UNPACKING THE MACHINE
The machine is delivered packed on pallet. To move it use a fork truck or a pulley block with sling.
To remove the package proceed as follows:
•
Remove the fixing tapes.
•
Remove the metal staples at package base.
•
Take the cardboard box off.
Package size: cm
153x76x119
Weight of packed machine FS50 B-BT:
P = 95 Kg
Weight of packed machine FS50 H-HT:
P = 103.5 Kg
2.
SLIDING THE MACHINE DOWN THE PALLET
•
Place a sliding board near the pallet.
•
Pull the machine backwards and make it pass over the blocking ledges.
•
Slide the machine down along the board.
3.
REFUELLIING (GAS ENGINE MACHINE ONLY)
ATTENTION: Before refuelling you should carefully read the information
contained in the engine’s specific OPERATING AND MAINTENANCE
INSTRUCTIONS, delivered together with the machine.