Performance test
Requirements:
Electrical installation at the control block must have been performed.
Pneumatic installation at the control block must have been performed.
Action sequence:
1. Switch on the operating pressure.
2. Apply operating voltage.
3. Check all possible switching position combinations of the two 5/2−way
solenoid valves V1 and V2 of the control block and the signals of the proximity
sensors E1 and E2 (here: PNP proximity sensors) using the following step
sequences. Pneumatic actuation of the working lines (2) and (4) is symbolised
through p2 and p4.
Individual time periods for the step sequences depend on the individual
application and are not considered here.
Содержание VOFA-B26-T52-M Series
Страница 26: ...VOFA Festo VOFA 1004NH Deutsch 26 Bild 11 Funktionstest Schritte 1 bis 4...
Страница 27: ...VOFA Festo VOFA 1004NH Deutsch 27 Bild 12 Funktionstest Schritte 5 bis 7...
Страница 64: ...VOFA Festo VOFA 1004NH English 64 Fig 11 Function test steps 1 to 4...
Страница 65: ...VOFA Festo VOFA 1004NH English 65 Fig 12 Function test steps 5 to 7...
Страница 79: ...VOFA Festo VOFA 1004NH de en 79...