25
UK
TECHNICAL SPECIFICATIONS
SUN G
14/2 PRO
Output
min
65,5
kW
max
155
kW
Flow
min
5,5
kg/h
max
13
kg/h
Functioning
Two stages
Fuel
Light oil
Max Viscosity at 20°C
1,5 °E - 6 CSt - 41 sec; R1
Electrical power supply
230/50 o 60 single-phase
V/Hz
1 stage / 2 stage pump calibration
10/18
bar
Motor
185
W
Max. absorbed power
345
W
Condenser
6,3
μF
Trasformator (voltage / secondary current)
26 / 48
kV/mA
Electric protection rating
20
IP
Noise level *
71
dB(A)
60° nozzle with vacuum / half-empty cone
2,00
GPH
Weight
15
kg
* Sound pressure measured in the manufacturer’s combustion laboratory, with burner operating on a test boiler
and at maximum output..
INSTALLATION ON TO THE BOILER
4
3
2
1
5
Fix flange 2 to the boiler using 4 screws 3 interposing the insulation gasket 4 and the possi
-
ble insulating cord 5. Insert the burner in the flange so that the draught tube penetrates into
the combustion chamber by the length suggested by the boiler manufacturer. Tighten screw
1 to lock the burner in position.