23
Edgebander
G 330 / G 360 / G 380
7.2 Setup
7.2.2 Setting up the edgebander
7.2.1 First cleaning of the machine
Any remants of protective oil must be removed from the
unvarnished surfaces before the machine is assembled.
Use a cleaning product such as an alkaloid (Turpentine
or Naptha).
Do not, however, spray any cleaning products onto the
machine. Wet a rag with the agent and then dispose of
the rag according to environment protection regulations.
The machine will, according to the form of transportation
used, be delivered either in cardboard or nylon
packaging, on a wooden pallet or in a wooden crate.
During transportation, some parts are dismantled to
avoid the possibility of damage during transportation.
When installing the machine, ensure that there is
sufficient space for the machine operator, including
the space required to move workpieces (loading,
processing, stacking) (see Fig.).
The machine stands must be on a smooth and even
surface. Use a spirit level to ensure that the work table is
level. Tolerance across the length ± 0.25 mm.
It is advisable to secure the machine to the floor using
the four holes which are already drilled in the machine
stand.
Fig. 7-1: Setting up the edgebander
Installation site requirements:
•
The installation site must be dry and weatherproof.
• Even, non-slip work surface.
• The installation site must be closed off or under sur-
veillance, so that children or unauthorised people
cannot gain access.
• The main switch with differential must be nearby.
• Operating/room temperature: +18° to +40° C
• Sufficient stability and load-bearing capacity of the
working area (approx. 800 kg/m²).
• Provide sufficient light at the workstation.
• Ensure there is sufficient clearance for or from
neighbouring workstations.
Setup and installation