 35B. THREE PHASE UNITS (except IST or STP units 

with VS2 or VS4 suffix): Connect the ground wire 

to the lug in the junction box. Connect any three 

wires from the pump to any three wires from the 

three-phase power source using the wire nuts 

supplied (from hardware pack p / n 400301902). 

Capacitors are not needed for three phase units. 

Install a pressure gauge in the line test port 

(see Figure 15), turn on the pump, and read the 

pressure gauge. Turn off the pump at the power 

supply, and change the connection of any two 

wires at the pump. Turn the pump back on and 

read the pressure gauge again. The electrical 

connection that gives the higher reading on the 

pressure gauge is the correct one.

 35C. IST UNITS or STP units with a VS2 or VS4 suffix: 

Connect the ground wire coming from indoors to 

the ground lug in the junction box. Connect any 

three wires from the pump connector assembly to 

the three power wires coming from the Variable 

Frequency Controller (VFC). Capacitors are 

not needed for these units. Detailed installation 

instructions for the VFC should be referenced 

when connecting the VFC. These are supplied 

with the VFC.

Not installing a ground wire increases 

the risk of lethal electric shock and 

equipment failure. All holes of the 

compression seal (contractors plug) 

must be filled with wires or a celcon rod 

to enable it to seal. 

 36.  Replace the junction box cover and tighten 

securely.

The pump discharge manifold has 

two labeled ports: one for the syphon 

system and one for the tank. A piston 

leak detector must be vented to the tank 

port (lower port) only. Do not connect a 

piston leak detector to the syphon port 

because this will make the leak detector 

inoperative, resulting in an increased 

risk of contamination of the environment 

(see tank port in Figure 14).

 37.  Connect power to the submersible pump at the 

electrical supply box.

 38.  Test proper operation by dispensing product into 

calibration can.

 39.  Turn off the dispenser switch. Feel the 

submersible pump to make sure that the pump has 

stopped running.

Note:

  If the pump does not turn off when the dispenser 

switch is turned off, this may indicate an electrical 

problem in the dispenser or other wiring error or 

malfunction. Call this to the immediate attention of 

a qualified electrician.

 40.  Visually check for leaks on the manifold head 

during pump operation and after.

 41.  Install a pressure gauge in the line test port to 

ensure that the STP / IST is providing proper line 

pressure. 

 42.  Turn on the STP / IST. While running, the pressure 

should be above 24 psi (1.65 bar). PMA size will 

affect psi. 

 43.  Turn off the STP / IST and verify that the line 

pressure is holding. 

 44.  Remove the pressure gauge and replace the plug. 
 45.  Turn on the STP / IST and, again, visually check for 

any leaks.

Warning

Caution

Содержание STP

Страница 1: ...ixed Variable Length Installation and Owner s Manual 2009 400604005 Rev 15 Franklin Fueling Systems 3760 Marsh Rd Madison WI 53718 USA Tel 1 608 838 8786 800 225 9787 Fax 1 608 838 6433 www franklinfu...

Страница 2: ...toring equipment is often housed in containment sumps designed to trap hazardous liquid spills and prevent contamination of the environment and as a consequence containment sumps can trap dangerous am...

Страница 3: ...e PEI RP100 Latest Edition Recommended Practices for Installation of Aboveground Storage Systems for Motor Vehicle Fueling The Petroleum Equipment Institute PEI RP200 Latest Edition Installation of Un...

Страница 4: ...the discharge casting Improper alignment could damage the wire lead or motor pins Failure to push PMA up snug against the discharge casting before tightening cap screws or failure to use a cross patte...

Страница 5: ...ser thread engagement 1 6 Length bottom of riser to end bell 90 Figure 5 Measure Tank 16 Hold the manifold securely to the surface to prevent damage while setting length To allow movement of the teles...

Страница 6: ...rdware pack p n 400301903 as shown in figure 10 Figure 10 Wire Through Contractor s Plug 22 Using the screwdriver slide the contractors plug into its seat in the discharge manifold Tighten the two scr...

Страница 7: ...the loosening direction during the tightening process may scrape away the thread sealing compound making it impossible to perform a tank tightness test This may also create a potential site for fuel...

Страница 8: ...t be filled with wires or a celcon rod to enable it to seal 36 Replace the junction box cover and tighten securely The pump discharge manifold has two labeled ports one for the syphon system and one f...

Страница 9: ...60 Hz capacitor Use a 40 F 370 V single phase 60 Hz capacitor Use a 15 F 440 V single phase 50 Hz capacitor Use a 40 F 440 V single phase 50 Hz capacitor 190 V 70 Hz 3 ph power to variable speed unit...

Страница 10: ...ssure relief valve in the check valve so it does not relieve line pressure back to the tank Syphon Systems Optional Syphoned tanks should be of the same diameter with tank bottoms located on the same...

Страница 11: ...11 Wiring Diagram 1...

Страница 12: ...e For further wiring diagrams see installation and owners manuals that came with pump controller Wiring must conform to all federal state and local electrical codes Contact FE Petro Technical Support...

Страница 13: ...g 17 400600002 5 16 24 x 7 16 Set Screw for VL units only 3 18 400333015 O Ring Motor Discharge 1 19 400264009 5 16 18 x 1 1 8 Socket Head Cap Screw 4 20 400263004 5 16 High collar Lock Washer may pur...

Страница 14: ...0280001 3 8 Standard Flat washer may purchase locally 2 10 400651930 Junction Box Assembly includes two of each Item 7 8 9 1 11 400210212 O Ring 2 Item Part Description Qty 13 400200930 Wire Connector...

Страница 15: ...1 Bracket Power Switch 1 3 400158901 Light Assembly 120V CBS 1 400158902 Light Assembly 240V CBBS 1 4 400215931 Relay 30A 120V 1 400215933 Relay 30A 240V 1 5 400278005 Terminal Strip 1 6 402410001 Lab...

Страница 16: ...est port NPT Vapor Recovery Discharge Port 1 NPT Riser Column Pipe Centerline Riser Column Pipe Centerline 11 70 7 55 R 10 45 8 12 R 3 00 5 80 3 63 Leak Detector Port 2 NPT Discharge Outlet 2 NPT 12 5...

Отзывы: