Installing the Virtual Services Platform 4000
power supply
You must install at least one power supply before using the switch. VSP 4000 models support two
field replaceable external power supplies. If supported, you can install an optional second power
supply for redundancy, load sharing, or to provide additional PoE+ power budget.
Perform the following procedure to install an external power supply into your switch.
Note:
VSP 4000 hardware can vary. This procedure only applies to hardware models with field
replaceable power supplies.
1. If a blanking plate covers the required power supply slot, remove the blanking plate before
attempting to insert the power supply.
2. Insert each power supply into a rear power supply slot.
3. Verify that each power supply is fully seated in the slot. Secure the power supply with the two
thumb screws.
Note:
The switch chassis can prevent an incorrect installation of a power supply. If you insert a
power supply upside down, it will not fully insert and the thumb screws will not engage.
4. Once you install a power supply, you can proceed with connecting AC power.
Note:
Do not connect an AC and DC power supply in the same chassis. Load sharing may be
affected.
Important:
You can hot swap power supplies while the switch is operational. One power supply is required
for continued switch operation. PoE+ load reductions can occur if you remove one power supply
while the switch is operating with dual power supplies.
Connecting to AC power
To connect AC power to the switch, you need an appropriate AC power cord as described in the
following table, also see the following table for plug specifications.
November 2017
Installation Job Aid for VSP 4450GSX Series
10