Instruction Manual ZHK
80/140
V07-21.0
Figure 178:
Pressure side execution
Figure 179:
Pressure side installation: remove the black closing plug
6.4 Duct connection
–
airside connection to AHU
Depending on the customer's requirements, EUROCLIMA devices are equipped with various ac-
cessories and options for attaching air duct elements like dampers, flexible connections, frames,
panel flanges, etc.
If no such accessories are supplied, then the airside mounting of components of the duct system is
made directly to the housing of the AHU. Depending on the device opening, this can be done di-
rectly on the panel flange or directly on the external panel of the device.
When connecting, make sure that the requirements listed below are followed:
6.4.1 Requirements
-
Ensure proper performance of the AHU by avoiding excessive pressure drops in the duct. To
minimize the noise, the basic principles of the duct construction and acoustic design must be
followed.